14. Maintenance
MiR1000 Shelf Lift User Guide (en) 12/2020 - v.2.1 ©Copyright 2019-2020: Mobile Industrial Robots A/S.
217
14.2 Regular checks and replacements
Before starting replacement tasks that involve removal of the top cover or side hatches:
•
Shut down the robot—see
Shutting down the robot on page 65
.
•
Disconnect the battery—see
Disconnecting the battery on page 68
contains the parts that you should check and how often you should do that.
Part
Maintenance
Interval
Lift cover
Check mounting. Ensure it sits
evenly on top of the robot.
Check monthly, and replace as
needed.
Safety PLC
In the robot interface under
Monitoring > Hardware health
> Communication
, see if the
robot is running with the correct
SICK configuration or if the
warning
The SICK Safety PLC is
running a non-standard
configuration
is shown.
Check monthly and after
commissioning or if you make
any changes to the robot setup.
Robot
hardware
In the robot interface under
Monitoring > Hardware health
,
check if there are any warnings
(marked with yellow).
Check monthly and after
commissioning or if you make
any changes to the robot setup.
Loudspeaker
and signal
lights
Check that all visual and auditory
warnings function.
Check monthly, and replace as
needed.
Swivel wheels
(the four
corner wheels)
Check bearings and tighten, and
check the wheels for wear and
tear.
Check weekly, and replace as
needed.
Drive wheels
(the two
middle-wheels)
Check wheel surfaces for wear.
Check every six months, and
replace as needed.
Table 14.2.
Regular checks and replacements