6. Getting started
MiR250 Shelf Carrier User Guide (en) 03/2021 - v.1.4 ©Copyright 2021: Mobile Industrial Robots A/S.
71
d.
Once the pins are lowered, verify that
2
under
Inputs
is green.
If the lift was raised and lowered as expected and the correct input feedback was received,
MiR Shelf Carrier 250 is correctly installed.
If MiR Shelf Carrier 250 did not operate correctly, verify that you have enabled the feature
as described in
Enable the MiR250 Shelf Carrier feature on page 67
. If MiR Shelf Carrier 250
continues to fail, contact your distributor.
6.12 Shutting down the robot
To shut down MiR250 Shelf Carrier, follow these steps:
1.
Ensure that the robot is not moving or executing an action.
2.
Press the Power button for three seconds.