23
Wiring and Address Setting
<a. Indoor/Outdoor Transmission Lines >
Connect A, B terminals of indoor/outdoor transmission line terminal board (TB3) on the outdoor unit and A, B
terminals of the Indoor/outdoor transmission terminal board (TB5). (Non-polar 2 wire)
✻
Only use shield line.
[Grounding the shield line]
Connect the earth terminal of the OC and S terminal of the IC terminal board (TB5).
<b. Transmission Line for Centralized Control >
Connect A terminals of centralized control transmission line terminal board on each of the outdoor units with each
other.
Do the same with B terminals. Replace CN41 (power supply switch connector) with CN40 on only one OC.
✻
Only use shield line.
[Grounding the shield line]
Connect S terminals of the TB7 of each of the outdoor units with each other.
Connect the S terminal of TB7 on the outdoor unit whose CN41 was replaced with CN40 to the earth terminal of
the electric box.
<c. Switch Setting >
Set the address as follows.
MA
remote
controller
Sub Controller
Main Controller
MA
MA
3
n/a
Main
Unit or Controller
Address
Setting Range
Steps
Factory
Setting
Setting Procedures
Indoor
Unit
Outdoor Unit
Main Unit
IC
OC
1
2
Remarks
51 ~ 100
Sub controller
01 ~ 49
00
00
Set the address for the controller at the
top of the indoor unit. Start with "01"
then use sequential odd numbers
(i.e.01, 03, 05).
Add 50 to the address assigned to the
indoor unit within the same refrigerant
system.
Use dipswitch to set the controller as
sub controller.
-
Sub Unit
IC
02 ~ 50
Add 1 to the address assigned to the
main unit in the same room.