P a g e | 17
3.4.4
Finishing the wall
Make sure the protective cardboard and the
protective film are in place before completing the
drywall installation. It is important that drywall
finishing debris and overspray does not get applied
to the fireplace surfaces or interior components.
3.4.4.1
Drywall Stops
Install drywall to the drywall stops along the
perimeter of the fireplace display insert (see Figure
21).
NOTE:
DO NOT DRILL OR SCREW INTO THE
FIREPLACE CHASSIS.
3.4.4.2
Drywall Placement
To secure the drywall, use a small amount of
construction strength adhesive to bond the drywall to
the front panel surface.
Make sure that the drywall does not go past the
drywall stop.
3.4.4.3
Construction Barrier
After the fireplace is installed, the drywall is finished,
construction is complete, and there is no debris on
the site, remove the cardboard construction barrier
from the front (see Figure 21).
Then carefully remove the protective film from the
media bed by removing the tape holding it in place.
3.4.5
Final start-up procedure
Make sure all connections and the fireplace itself
have been thoroughly cleared of dust and debris
before beginning the start-up procedure.
3.4.5.1
Filling the Reservoir
If using the manual water fill method, proceed as
follows: With the glass door open, lift the water fill
flap located on the left side of the media bed (see
Figure 22) and add about 3 gallons of clean water to
the reservoir. Do not fill beyond the max fill indicator.
The display will indicate each time more water is
needed.
Figure 21
Figure 22
Summary of Contents for FusionFire 60
Page 9: ...P a g e 9 Figure 7 ...