©MODUPLAY 2011
PH: 02 4272 1644
DWG NO.
ACTIVITY NAME:
Summary Install Guide
1. Dig and pour main footing; Dig holes for strut footings but do not pour
2. let concrete set for minimum 72 hours
3. Erect large pole and bolt to footing
4. Bolt Struts onto main pole and bolt strut footing on. pour the strut footings
5. Allow concrete to set for minimum 72 hours
6. Bolt swing hanger to main pole and assemble chains and seat. ensure seat
has a minimum 500mm clearance from finished soft-fall level. You may have to
shorten chains to achieve this.
XSWA 1009
Mammoth Swing 4500
300
1000
2000
300
600
2 x M30 Bolts per Strut
8 x M30 Bolts
4 x M24 Bolts
per Strut
Pole Footing
Strut Footing
570 kg
70 kg
215 kg
22 kg
Finished Soft-Fall Level
4500
2000L x 1500W x 1000H
Concrete Footing
800L x 800W x 600H
Concrete Footing
610