INSTALLATION FOR VERTICAL TERMINATION
1. Determine the route your vertical venting will take. If ceiling joist,
roof rafters or other framing will obstruct the venting system,
consider an offset.
See Figure 31
to avoid cutting load bearing
members.
NOTE: Pay special attention to these installation instructions
for required clearances (air space) to combustibles when
passing through ceilings, walls, roofs, enclosures, attic
rafters, etc. Do not pack air spaces with insulation. Also
note maximum vertical rise of the venting system and any
maximum horizontal offset limitations. Offsets must fall
within the parameters shows in Figure 14, page 18.
2. Set fireplace in desired location. Drop a line plumb down from
the ceiling to the position of the flue exit. Mark the center point
where the vent will penetrate the ceiling. Drill a small locating
hole a this point.
Drop a plumb line from the inside of the roof to the ceiling locat-
ing hole in the ceiling. Mark the center point where the vent will
penetrate the roof. Drill a small locating hole at this point.
FLAT CEILING INSTALLATION
1. Cut a 9
1
/
2
" (241mm) square hole in the ceiling using the locat-
ing hole as a center point The opening should be framed to
9
1
/
2
"x9
1
/
2
" (241mm x 241mm) inside dimensions as shown in
Figure 32
using framing lumber the same size as the ceiling joist.
If the area above the ceiling is an insulated ceiling or a room, nail
firestop from the top side. This prevents loose insulation from fall-
ing into the required clearance space.
See Figure 32.
Otherwise,
install firestop below the framed hole. The firestop should be
installed with no less than three nails per side.
See Figure 33.
2. Assemble the desired lengths of pipe and elbows necessary to
reach from the burner system flue up through the firestop. Be sure
pipe and elbow connections are fully twist-locked.
See Figure
17, page 19.
3. Cut a hole in the roof using the locating hole as a center point.
(Cover any exposed open vent pipes before cutting hole in roof).
The 9
1
/
2
"x9
1/
2
" (241mm x 241mm) hole must be measured on the
horizontal. Actual length may be larger depending on the pitch of
the roof. There must be a 1" minimum clearance from the vent
pipe to combustible materials. (Insulation should be considered
a combustible material) Frame the opening as shown in
Figure
16 on page 19.
Figure 31 - Offset with Wall Strap and 45°
Elbows
Roof
Flashing
Wall
Strap
45° Elbows
Ceiling Firstop
Figure 32 - If area above is a room, install
firestop above framed hole as shown
Figure 33 - If area above is not a room, install
firestop below framed hole as shown
Continued on next page
Firestop
Nails
Nails
Firestop
Summary of Contents for SDV500
Page 46: ...46 56D0106 1 2 3 11 6 7 8 5 4 9 10 ILLUSTRATED PARTS LISTS FIREBOX COMPONENTS ...
Page 48: ...48 56D0106 1 2 3 6 4 5 ILLUSTRATED PARTS LISTS ADDITIONAL ACCESSORIES ...
Page 52: ...52 56D0106 ILLUSTRATED PARTS LISTS 1 2 3 4 5 6 7 9 ELECTRONIC IGNITION 8 10 11 L O HI ...
Page 57: ...56D0106 57 NOTES ...