Installation
Section 3-2: Installing a Roof Mounted Direct Vent Termination
(PVTK-1)
This section applies to installations where the direct vent termination
will be roof mounted.
Section 3-2-1: Venting Layout
Selection of components and details of venting lay out should
adhere to the following guidelines:
The maximum termination point is 32’ above the fireplace (NOTE:
if the maximum termination height is used, the flame pattern
may be affected).
The Vertical termination must be a minimum 2’ higher than where
the termination exits the roofing materials, (asphalt shingles,
cedar shakes, etc). This distance should be measured from the
high side of the roof slope where the flue flashing intersects the
roofing materials. (see
Figures 10 to 10c
).
Termination location must be a minimum 6’ from a mechanical
air inlet.
Termination location must be a minimum 18” from a parapet wall
For a more detailed diagram of allowed termination locations,
see
Appendix A
.
A maximum of two offsets (each offset is made up of 2-90°
bends) may be made for vertical vent runs.
Firestops must be installed as required by National & local codes.
Ensure all horizontal runs are supported with a minimum of 3
supports per 10’ of venting.
Install all roof flashing and storm collars as shown.
Figure 10
.
Top vent, Roof mounted
termination with no offset in vent run.
Figure 10a.
Top vent, Roof mounted
with 1 offset (1 offset= two
90° bends).
Figure 10b.
Top vent, Roof mounted
with 2 offsets (1 offset= two
90° bends).
Roof mounted Terminations
The following details are some possible configurations for Roof
mounted terminations.
PVTK1 Termination
PVTK1 Termination
PVTK1 Termination