P/N XG0206
Page 14
M40DV-CR/CL Corner Gas Fireplace
Installation
Wiring
Gas Control and Pilot Wiring
Figure 21. Wiring for the M40DV-CR/CL-I with Honeywell gas control
and pilot.
M40DV-CR/CL-I
Removing and Installing the
Glass Doors
Removing the Louvres and Side Panels
Rotate the upper end louvre assembly approximately 110° (as shown
in figure 22a, step
). Pull the assembly towards you to remove it
from the fireplace.
Repeat this for the lower end louvre assembly.
Remove the louvre assemblies (upper and lower) from one side of the
fireplace. Grasp the assembly underneath one of the louvres and up
slightly and pull outwards, as shown in figure 22a.
Remove the side panel by sliding it out and away from the back of the
fireplace. Refer to figure 22b.
Removing the Doors
Figure 22a. Removing the louvre assemblies.
Figure 22b. Removing the side panel.
To remove the inner doors, simply unscrew the eight (8) machine
screws on the top and bottom of the door.
(See figure 22c).
Door Installation
To re-install the doors, align the door with the screw holes and
re-fasten with all eight machine screws. Ensure that a good seal is
maintained.
Re-install the side panels and louvre assemblies by reversing the
above steps.
Figure 22c. Removing the door.
Figure 20c. When using a tile surround, do not tile over the outside
Honeywell (Q3450)
Pilot Assembly
Pilot Electrical
Harness Connector
Honeywell Gas
Control (SV9501M)
Gas Control
Connector
Junction Box
115VAC
24VAC
40 VA
Transformer
Black
White
Green
Gnd Screw
Wall Switch
Fan Plug
Receptacle