Page 12
P38DF* Indoor Gas Fireplace
XG0193 - 103111.1
Installation
The Venting graph:
Measure the vertical height from the fireplace hearth to the centre of
the termination and the horizontal run from the fireplace flue collar to
the wall flange of the termination. Plot on the Venting Graph
Figure 12
or 12a
with an 'X'.
If the 'X' falls on or above the top boundary of the shaded area, the
installation is acceptable.
Example A: (Acceptable Installation)
If the vertical dimension from the hearth is 120" and the horizontal
run to the wall flange of the vent termination is 144", this would be
an acceptable installation.
Example B: (Unacceptable Installation)
If the vertical dimension from the hearth is 36" and the horizontal
run to the wall flange of the vent termination is 84",
this would not
be an acceptable installation.
Example C: (Unacceptable Installation)
If the vertical dimension from the floor of the fireplace is 60" and
the horizontal run to the wall flange of the vent termination is 144",
this would not be an acceptable installation.
Figure 13.
Top Vented, wall mounted installation with one 90° bend.
The vent run must comply with Venting Graph for Top vent, wall
mounted terminations, Figure 12 or 12a.
Figure 13a.
Top Vented, wall mounted Multi-elbow installation. See
Venting Graph for Top vent, wall mounted terminations,
Figure 12 or 12a
.
Section 3-3-1: VEnTIng LAYOUT: Wall mounted termination.
Selection of components and details of venting layout should adhere
to the following guidelines:
Vent terminations must not be recessed in walls or siding.
For Heat Shield requirements see
Section 3-3-3
on
page 16
.
Once the proposed venting layout has been determined refer to
Figure 12, 12a, 15, or 15a
to ensure the layout is acceptable.
notes Wall Mounted Terminations:
TOP VENT
All measurements for vertical or horizontal runs are measured
from center of the vent pipe.
Venting runs
must
fall within the limits set by the venting graph,
see
Figure 12 or 12a
.
Wall mounted Terminations
The following details are some possible configurations for Wall mounted
terminations. See below.
Figure 12.
P38DF* LP Top Vent
Venting Graph for
wall mounted
terminations.
Figure 12a.
P38DF* NG Top Vent
Venting Graph for
wall mounted
terminations.
WARNING:
An inspection of the explosion relief flappers and door
MUST
be
made prior to lighting the fireplace. A faulty seal on the door gasket ...
and/or explosion ports will result in products of combustion leaking
into the living space and may result in carbon monoxide poisoning.
Heat
Shield
Termination
Hearth
Exterior
Wall
39" Min. (NG)
44" Max. (NG)
Flex section
63" Min. (LP)
16" Max. (LP)
Solid Section
Flex Section
Hearth
30”min
15’Max.
Heat
Shield
Termination
Exterior
Wall
8' MIN AT MAX
Horizontal
44”
39”
A
C
B
Unacceptable vent run
within shaded area.
Acceptable vent run
within non-shaded area.
If your installation does not fall
within the venting parameters,
please contact a local Montigo
dealer for Power Venting options.
16”
63”
A
C
B
Unacceptable vent run
within shaded area.
Acceptable vent run
within non-shaded area.
If your installation does not fall
within the venting parameters,
please contact a local Montigo
dealer for Power Venting options.