1.
Locate ceiling joists and pre-drill
six 1/4”
holes
(depending on your
joist spacing) for 3/8” lag screws
approximately
2”
deep on
16”
centers.
2.
Place 6 large eye
lag bolts 6” outside the previously
pre-
drilled lag screw holes as shown.
3.
While the machine is still on the ground, plug the machine
in and unwind straps until fully extended.
4.
Flip the machine so that the motor and components are
touching the floor.
5.
Connect extended straps to eye bolts and lift the hoist to
the ceiling by pressing the up button on the remote or
pendant (this keeps the hooks on the machine from
jamming or catching in the machine spools while lifting).
Be sure the straps wind up level on the spools.