User Guide: PTP 600 Series
Task 8: Align antennas
phn-0896_012v000
Jul 2010
6-71
Task 8: Align antennas
This task consists of the following procedures:
•
Starting up the units
on page
6-71
•
Using the graphical installation option
on page
6-72
•
Using the ODU installation tones
on page
6-73
•
Aligning the units
on page
6-74
•
Observing behavior during alignment
on page
6-75
•
Aligning connectorized antennas
on page
6-76
Before performing this task, check that hardware installation is complete at both the
Master and Slave sites, apart from the network connections.
Starting up the units
To connect one of the units to a management PC and start up both units, proceed as
follows:
Procedure 6-27 Starting the units after site hardware installation
1
Select the unit from which this process is to be controlled; either
Master or Slave. This is the ‘local’ unit.
2
Check that the management PC is connected to the local unit,
powered up and logged on.
3
Start the local unit.
4
Start the remote unit.
5
Log into the local unit as described in
Logging into the web
interface
on page
6-4
.