PAGE 44 — DCA125SSIU 50 HZ GENERATOR • OPERATION AND PARTS MANUAL — REV. #0 (12/22/08)
TRAILER MAINTENANCE
Lug Nut Torque Requirements
It is extremely important to apply and maintain proper wheel
mounting torque on the trailer. Be sure to use only the
fasteners matched to the cone angle of the wheel. Proper
procedure for attachment of the wheels is as follows:
Start all wheel lug nuts by hand.
1.
Torque all lug nuts in sequence (see Figure 60).
2.
DO
NOT
torque the wheel lug nuts all the way down.
Tighten each lug nut in 3 separate passes as defi ned
by Table 16.
After fi rst road use, retorque all lug nuts in sequence.
3.
Check all wheel lug nuts periodically.
Tire Torque Requirements
Table 16.
Wheel Size
First Pass
FT-LBS
Second Pass
FT-LBS
Third Pass
FT-LBS
12"
20-25
35-40
50-65
13"
20-25
35-40
50-65
14"
20-25
50-60
90-120
15"
20-25
50-60
90-120
16"
20-25
50-60
90-120
Wheel Lug Nuts
Figure 60.
Tightening Sequence
NOTICE
NEVER
use an pneumatic air gun to tighten wheel
lug nuts.
Summary of Contents for WHISPERWATT DCA125SSIU
Page 19: ...DCA125SSIU 50 HZ GENERATOR OPERATION AND PARTS MANUAL REV 0 12 22 08 PAGE 19 NOTES ...
Page 54: ...PAGE 54 DCA125SSIU 50 HZ GENERATOR OPERATION AND PARTS MANUAL REV 0 12 22 08 GENERATOR ASSY ...
Page 56: ...PAGE 56 DCA125SSIU 50 HZ GENERATOR OPERATION AND PARTS MANUAL REV 0 12 22 08 CONTROL BOX ASSY ...
Page 58: ...PAGE 58 DCA125SSIU 50 HZ GENERATOR OPERATION AND PARTS MANUAL REV 0 12 22 08 CONTROL BOX ASSY ...
Page 60: ...PAGE 60 DCA125SSIU 50 HZ GENERATOR OPERATION AND PARTS MANUAL REV 0 12 22 08 CONTROL BOX ASSY ...
Page 68: ...PAGE 68 DCA125SSIU 50 HZ GENERATOR OPERATION AND PARTS MANUAL REV 0 12 22 08 BATTERY ASSY ...
Page 70: ...PAGE 70 DCA125SSIU 50 HZ GENERATOR OPERATION AND PARTS MANUAL REV 0 12 22 08 MUFFLER ASSY ...
Page 72: ...PAGE 72 DCA125SSIU 50 HZ GENERATOR OPERATION AND PARTS MANUAL REV 0 12 22 08 FUEL TANK ASSY ...
Page 87: ...DCA125SSIU 50 HZ GENERATOR OPERATION AND PARTS MANUAL REV 0 12 22 08 PAGE 87 NOTES ...