Step 12:
Attach Burner Assembly to the Post (3 bolts
1/4
"
-20
×1
/2
"
& 3 flat washers)
Step 13:
Attach Dome to the Emitter (3 round-head nuts
M8 & 6 flat washers)
Step 14:
Connect the Hose and Regulator
Assembly to the Flare Fitting on the Gas Line and
tighten.
Step 15:
Leak Test #2:
*Attach the regulator to the Propane Cylinder.
*Apply several drops of the Leak Check Solution (Step
10) to the hose / gas line connection.
*Make sure the Heater Control Knob is “OFF”.
**”Open” the Propane Cylinder Valve.
*If bubbles appear at the connection, there is a leak and
it must be tightened until no bubbles appear. MAKE
SURE THERE IS NO LEAKS.
*”Close” the Propane Cylinder Valve, then disconnect
the Hose and regulator Assembly from the Propane
Cylinder and the Gas Line