Operating Instructions

10

11

33. Carry out the cleaning operation 

using the cleaning inspection 

machine equipped with nylon wire 

brush (

N.

).

34. Proceed with stopping operation.
35. Check the operation of the 

expanding stopper. If the sealing 

ring does not expand evenly on 

the entire perimeter, it is necessary 

to lubricate the walls surrounding 

the ring with PURITY-FG Spray or 

equivalent (walls are compressed 

by two steel flanges). Expand and 

retract the sealing ring a few times 

until the expansion is uniform. In the 

event that the stopper is not used 

for a long time, it is recommended to 

completely disassemble the stopper, 

replace the sealing ring and lubricate 

thoroughly. After reassembling the 

stopper, wipe the outer side of the 

ring that comes into contact with the 

inner side of the pipe. 
36. Clean and lubricate the stopper 

bar and the sealing disk to provide 

smooth operation and to allow 

centering of the stopper during the 

expansion phase.
37. Position the stopping machine 

(

O.

) on the slide gate valve. 

NOTE: There are 2 handles on the 

stopping machine. The longer one 

should always be on the upstream 

side.

P.

   

Equalization Valve

Counter-

clockwise

42. Purge the air in the bypass 

through the drain valve located on 

the downstream stopping machine.
43. Open the second slide gate 

valve without acting on the internal 

pressure equalizer, as pressure is 

already equal above and below the 

gate.
44. Ensure the proper operation of 

the bypass and check for leaks.
45. Leaving the safety ring loose, 

lower the stopper and position the 

long handle between the pins on the 

saftey ring. If this is difficult, repeat 

previous step taking care to ensure 

the plug is at a 90° position with 

respect to the pipe axis. Once the 

hole has been passed, place the 

plug in the direction of the pipe axis.
       CAUTIoN: The plug should 

never be inserted and expanded 

on the upstream side. 
46. 
Turn the ratchet handle 

clockwise and gradually expand the 

sealing ring of the stopper. During 

this operation slide the rod from top 

to bottom and vice versa to properly 

position the stopper in the pipe (

Q.

). 

47. Expand the sealing ring to 

obtain a positive shut-off. DO NOT 

overtighten.
       CAUTIoN: The torque applied 

to the ratchet spanner should not 

exceed 52 ft-lb for the 8" plug.
The torque applied to the ratchet 

spanner should not exceed 74 ft-lb 

for the 12" plug.

38. Perform the same operations 

on the second fitting and install the 

bypass between the two machines. 

Equalize the pressure (

P.

) of the first 

slide gate valve. For this operation 

rotate the knob that controls 

equalizing valve counter-clockwise 

until it stops.
39. Open the slide gate valve.
40. Open the machine bypass.
41. Open the machine bypass 

located on the second stopping 

machine.

!

!

O.

Long Handle

Short 

Handle

N.

Cleaning /

Inspection

Machine

with

Viewer

Brush

!

Q.

Long Handle

Short 

Handle

Summary of Contents for ShurStop 812 PE

Page 1: ...ty damage 3 Safety goggles and other appropriate protective gear should be used Failure to do so could result in serious injury 4 Pressure test check for and repair leaks in all fittings and component...

Page 2: ...re of 125psig Actual MAOP will be dependent on the operating pressure of the PE pipe This manual describes all operations including drilling stopping and completion plug insertion Basic Equipment Requ...

Page 3: ...ectrofusion housing with metal bushing Completion plug with two O rings Completion cap with one O ring NOTE These fittings are compatible with any universal processor available on the market equipped...

Page 4: ...he valve is fitted with an internal pressure equalizer which allows easy opening when pressure varies between the upper and lower parts of the valve To open and close the valve turn the operating squa...

Page 5: ...ll be working It also allows inspection of the fittings internal threads and cleaning if necessary before installing completion plug Cleaning Inspection machine H L W Bleed Valve Brush Rod Viewer insi...

Page 6: ...until the pipe holder is in contact with the pipe D D1 CAUTION The best compression is the one where it is impossible to insert a sheet of paper between the fitting and the pipe 5 Perform the electro...

Page 7: ...ur Stop TM Unit 812 PE Line Stopping System Operating Instructions 7 G PE Pipe 8 12 20 Vent Fitting H Combined Wrench A1 A Pilot Bit Allen Key for tightening B Shell Cutter Adjustment Flange Eyebolt S...

Page 8: ...13 Insert the removable handle in the drilling machine 5 Lift and position the drilling machine onto the slide gate valve in the open position Tighten the bolts in a criss cross fashion C CAUTION Afte...

Page 9: ...d out J 22 Loosen the knob on the graduated scale turn the graduated scale 90 counter clockwise and then tighten the knob K J Collar 23 Open the oil flow and begin drilling again until the pipe coupon...

Page 10: ...gate valve without acting on the internal pressure equalizer as pressure is already equal above and below the gate 44 Ensure the proper operation of the bypass and check for leaks 45 Leaving the safet...

Page 11: ...out of the vent No 2 close the respective gate valve letting the gas equalize pressure It is now possible to test the new connections T 54 Decompress the sealing ring of the stopper by operating coun...

Page 12: ...d check the completion plug for leaks MUELLER Shur Stop TM Unit 812 PE Line Stopping System Operating Instructions 12 Preparation of Drilling Machine To Insert Completion Plug 1 Attach completion plug...

Page 13: ...nspection cleaning machine Inadequate sealing of the Insufficient tightening of the screws sealing disk of the flange that compresses the Tighten the screws slightly sealing disk Inadequate sealing of...

Page 14: ...MUELLER Shur Stop TM Unit 812 PE Line Stopping System Notes 14...

Page 15: ...MUELLER Shur Stop TM Unit 812 PE Line Stopping System Notes 15...

Page 16: ...s document herein are the property of Mueller Co LLC its affiliates or other third parties Products marked with a section symbol are subject to patents or patent applications For details visit www mwp...

Reviews: