 Unit 812 PE Line Stopping System

Equipment, Parts and Dimensions

4

5

4. Stopping Machine

The Stopping Machine is composed 

of:
• A stopping machine with bypass 

valve, bleed valve and available gas 

source (equalizer);
• An expanding stopper consisting of 

two flanges.
On the upper part of the stopping 

bar there is an operating square that 

when turned (clockwise) the two 

flanges compress resulting in the 

expansion of the sealing ring.
The result is full contact between the 

sealing ring and the inner wall of the 

pipe, ensuring complete gas control 

The affect is 100% stop off.

3. Slide Gate Valve

The Slide Gate Valve consists of a 

sliding gate housed between two 

flat bodies; pressure is held firmly 

by two O-rings, one above and one 

underneath. The valve is fitted with 

an internal pressure equalizer which 

allows easy opening when pressure 

varies between the upper and lower 

parts of the valve. To open and close 

the valve, turn the operating square 

approximately a quarter turn.
       CAUTIoN: Never leave the 

valve with the gate in the closed 

position when not in use. In 

the event that the gate is stuck, 

loosen the screws holding the two 

valve bodies, bring the gate to the 

open position and retighten the 

screws.

DIMENSIoNS – Inches (mm)

 

PE PiPE L 

H  

PASSAgE 

Ø

A WT – lbs (Kg)

  8" – 12"   29.23 (742.5)   21.81 (554)   8.00 (203.5)   10.90 (277)  172.0 (78)

slide gate ValVe

stopping maChine

!

DIMENSIoNS – Inches (mm)

 

PE PiPE L 

H  

WT – lbs (Kg)

  8"   23.42 (595)   16.92 (430)   41.92 (1065)   240.3 (109)
  12"   31.96 (812)   19.29 (490)   54.25 (1378)   481.6 (218)

Upper Valve Body

Equalization Valve

Upper Flange

Gate

Lower 

Flange

operating Square

Lower Valve Body

L

H

Long Handle

Safety Ring

Bypass

Throttle

Short Handle

W

Bleed 

Valve

Stopper

operating Square

Weights

Sealing Ring

Summary of Contents for ShurStop 812 PE

Page 1: ...ty damage 3 Safety goggles and other appropriate protective gear should be used Failure to do so could result in serious injury 4 Pressure test check for and repair leaks in all fittings and component...

Page 2: ...re of 125psig Actual MAOP will be dependent on the operating pressure of the PE pipe This manual describes all operations including drilling stopping and completion plug insertion Basic Equipment Requ...

Page 3: ...ectrofusion housing with metal bushing Completion plug with two O rings Completion cap with one O ring NOTE These fittings are compatible with any universal processor available on the market equipped...

Page 4: ...he valve is fitted with an internal pressure equalizer which allows easy opening when pressure varies between the upper and lower parts of the valve To open and close the valve turn the operating squa...

Page 5: ...ll be working It also allows inspection of the fittings internal threads and cleaning if necessary before installing completion plug Cleaning Inspection machine H L W Bleed Valve Brush Rod Viewer insi...

Page 6: ...until the pipe holder is in contact with the pipe D D1 CAUTION The best compression is the one where it is impossible to insert a sheet of paper between the fitting and the pipe 5 Perform the electro...

Page 7: ...ur Stop TM Unit 812 PE Line Stopping System Operating Instructions 7 G PE Pipe 8 12 20 Vent Fitting H Combined Wrench A1 A Pilot Bit Allen Key for tightening B Shell Cutter Adjustment Flange Eyebolt S...

Page 8: ...13 Insert the removable handle in the drilling machine 5 Lift and position the drilling machine onto the slide gate valve in the open position Tighten the bolts in a criss cross fashion C CAUTION Afte...

Page 9: ...d out J 22 Loosen the knob on the graduated scale turn the graduated scale 90 counter clockwise and then tighten the knob K J Collar 23 Open the oil flow and begin drilling again until the pipe coupon...

Page 10: ...gate valve without acting on the internal pressure equalizer as pressure is already equal above and below the gate 44 Ensure the proper operation of the bypass and check for leaks 45 Leaving the safet...

Page 11: ...out of the vent No 2 close the respective gate valve letting the gas equalize pressure It is now possible to test the new connections T 54 Decompress the sealing ring of the stopper by operating coun...

Page 12: ...d check the completion plug for leaks MUELLER Shur Stop TM Unit 812 PE Line Stopping System Operating Instructions 12 Preparation of Drilling Machine To Insert Completion Plug 1 Attach completion plug...

Page 13: ...nspection cleaning machine Inadequate sealing of the Insufficient tightening of the screws sealing disk of the flange that compresses the Tighten the screws slightly sealing disk Inadequate sealing of...

Page 14: ...MUELLER Shur Stop TM Unit 812 PE Line Stopping System Notes 14...

Page 15: ...MUELLER Shur Stop TM Unit 812 PE Line Stopping System Notes 15...

Page 16: ...s document herein are the property of Mueller Co LLC its affiliates or other third parties Products marked with a section symbol are subject to patents or patent applications For details visit www mwp...

Reviews: