background image

6 of 9

Part Number 020006402  12/2014

 

Air Compressor Kits

7.  Locate the three foot (0.91 m) length of tubing supplied 

with air compressor. Neatly route and attach this line 

from the air compressor tank compression elbow to the 

shutoff valve compression fitting located on top of the 

dump valve. Trim tubing to correct length.

8.  Locate the eight foot (2.44 m) length of tubing supplied 

with air compressor. Route and connect this line from 

the 1/4" (6.35 mm) barb elbow of the dump valve to a 

floor drain. Place the shut-off valve handle in the open 

position. (See Installation figure)

9.  Connect the air pump to the outlet box, following the 

electrical instructions below.

NSTALLATON OF MODEL 44KX REFRGERATON UNT

1.  Shut off main CO

2

 supply to refrigeration unit.

2.  Locate the air/CO

2

 change-over valve assembly 

supplied with kit P.N. 212506. Align the mounting 

bracket of the change-over valve over the mounting 

holes on control panel (Location for changeover valve 

will be marked “Air/CO

2

 Change-over Valve”). Mount the 

air/CO

2

 change-over valve to the panel with the #10-32 

screws provided in kit. (See figure below) 

To CO

2

 Supply 

Manifold

Air/ CO

2

 

Changeover 

Valve

To Outlet Fitting 

of Air Pump

To Syrup 

Tank Supply 

Manifold

Mpdel 44KX Mtaifplds

3.  Locate the 1/4" (6.35 mm) EVA line connected at the 

CO

2

 supply manifold and syrup tank manifold. Remove 

and discard the line.

4.  Connect the 1/4" (6.35 mm) line assembly provided in 

kit P.N. 212506 to the flair fitting on the right side of 

the air/CO

2

 change-over valve. Route the other end of 

the tubing to the CO

2

 supply manifold. Trim excess line 

and connect swivel nut adapter to the remaining end 

of line assembly. Secure with tab clamps. Connect this 

line assembly to the CO

2

 supply manifold. (See figure 

above)

5.  Locate the 4-1/2" (11.4 cm) section of 1/4" (6.35 mm) 

tubing and connect to the bottom side of the air/CO

2

 

change-over valve. Route and connect the remaining 

end of tubing to the syrup tank supply manifold. (See 

figure above)

6.  Locate the 12' x 1/4" (3.66 m x 6.35 mm) EVA line 

assembly provided in kit P.N. 212506. Attach the end 

of this line assembly, with the swivel nut, to the outlet 

fitting of the air compressor tank. Neatly route tubing 

under the stand top and to the left side of the control 

panel. Connect the line assembly with 1/4" (6.35 mm) 

elbow x barb (provided in kit P.N. 212506) to the 1/4" 

(6.35 mm) male flare fitting of the air/CO

2

 change-over 

valve. (See figure above)

7.  Locate the dump valve supplied with kit. Mount the 

dump valve with #10-32 self-tapping screws provided 

with kit to lower left cross channel of support stand. 

Use holes provided in channel. (See Installation figure)

8.  Locate the six foot (1.83 m) length of tubing supplied 

with kit. Neatly route and attach this line from the air 

compressor tank compression elbow to the shutoff 

valve compression fitting located at top of the dump 

valve. Trim tubing to correct length. (See Installation 

figure)

9.  Locate the eight foot (2.44 m) length of tubing supplied 

with kit. Route and connect this line from the 1/4" 

(6.35 mm) barb elbow of the dump valve to a floor 

drain. Place the shutoff valve handle in the open 

position. (See Installation figure)

10. Connect the cord to the stand outlet box or the wall 

outlet, following the appropriate steps listed below.

ELECTRCAL CONNECTONS (FOR BOTH MODELS 37KX 

AND 44KX)

This air pump kit is designed to easily connect to the high 

stand that supports the refrigeration unit Model 44KX 

or 37KX. The stand comes with an electrical outlet box 

mounted to it. However, should the pump be used with 

another type of stand, the power cord must be modified by 

adding a plug that is accepted by the local electric outlet.

Summary of Contents for 00212053

Page 1: ...le CO2 cylinders and gauges with care Secure cylinders properly against abrasion DO Store CO2 cylinder s in well ventilated areas DO NOT Throw or drop a CO2 cylinder Secure the cylinder s in an uprigh...

Page 2: ...sary do not connect the grounding wire to a flat blade terminal The wire with insulation having an outer surface that is green with or without yellow stripes is the grounding wire Check with a qualifi...

Page 3: ...2 section of 1 4 tubing connected at bottom side of change over valve Route and connect the remaining end of tubing to the syrup tank supply manifold refer to figure above 3 Locate the 12 ft x 1 4 EV...

Page 4: ...remaining end of the air line to the inlet and onto the outlet of the low pressure regulator Route and connect the remaining end of the tubing to the inlet side of the air filter assembly 4 Connect on...

Page 5: ...ply Manifold Air CO2 Change over Valve Retaining Ring Handle and Screw Model 37KX Manifolds 3 Locate the air CO2 change over valve supplied with the air pump installation kit P N 212508 Provided with...

Page 6: ...ifold See figure above 5 Locate the 4 1 2 11 4 cm section of 1 4 6 35 mm tubing and connect to the bottom side of the air CO2 change over valve Route and connect the remaining end of tubing to the syr...

Page 7: ...ave a ground wire connecting terminal 2 Locate the loose end of the power cord attached to the kit All three wires are stripped to 1 2 length from the end 3 Connect all three wires to plug using the 1...

Page 8: ...AIR COMPRESSOR TANK 1 Remove and discard the four 4 old well nuts from the stand s air compressor mounting brackets and replace with four 4 new well nuts provided in kit refer to figure 2 Position the...

Page 9: ...are provided for this purpose 2 Insert the rubber pads into the holes in the bracket that match the holes in the air pump 3 Position the air pump on the pads and screw in the bolts with washers Tight...

Reviews: