Step 5: Placing the gin-pole cables
1. Take the 6x19 8 mm cable (connection cable) with thimbles at each end and connect it with
M16 shackles to the 2
nd
segment lifting eye (pos 1) and the gin-pole lower lifting eye (pos 2)
(see Figure 9 and 10).
2. Take the 6x19 8 mm cable (lifting cable) with thimble at one end and a hook at the other end
and connect the thimble end with a M16 shackle to the gin-pole upper lifting eye (pos 3).
3. Make sure that all the shackles are securely fastened and that the cables do not have knots
or twists in them.
Connection cable
Lifting cable
Figure 9
– Cable ends
Figure 10
– Placing the gin-pole cables