3.2.4 Preparation for Installation
Installation
Space
Secure sufficient working space for easy operation, cleaning, maintenance, and inspection.
Lighting
Provide sufficient lighting to allow easy operation, cleaning, maintenance, and inspection.
Ventilation
If natural ventilation is insufficient, install ventilation fans according to the relevant regulations.
Piping
Refer to the relevant figures section 2.3.4"Outer Dimensions" in this manual.
3.2.5 Installation
Check that the surface of the package unit, where the compressor is to be installed, is even and
horizontal. If it is uneven and non-horizontal, tightening the bolts may lead to compressor deformation,
which may prevent normal operation.
3.2.5.1 Piping
Connection
Refrigerant
Piping
Observe the following when connecting the refrigerant piping.
The compressor is one of the few devices installed within the refrigerating/cold storage unit that
have moving components. These moving components are adversely affected by foreign
substances within the system (scale, dust, spatter, etc.). Therefore, when connecting the piping,
do not allow any of such foreign substances to enter inside.
Some compressors (mainly those for export) are charged with nitrogen gas to prevent rust. Be
sure to release the pressure before starting piping work.
Be sure not to allow moisture to enter the piping. There is a high probability that it will cause
trouble after the start of operation. Be sure to assemble piping when it is dry.
Improper piping may cause operating problems such as oil not returning to the compressor or
liquid flow-backs.
When connecting the piping to the compressor, use piping that is the same size as the
compressor connection port. If the pipe size of the piping is smaller than the compressor
connection port, the flow of lubricant or refrigerant will be obstructed leading to problems.
Do not let the weight of the piping connected to the compressor applied onto flanges or joints.
Be sure to prepare proper supports for piping.
3.2.5.2 Equipment and Devices for Protection of the Compressor
Oil
Filter
Use an oil filter with filtration accuracy of not higher than 15
μ
m and install it in front of the oil inlet of
the compressor.
The oil filter may be clogged just after test operation. We recommend installing two oil filters in
parallel. This will enable replacement of either filter during operation.
Oil Heater for Oil Separator
To preserve the temperature of the lubricant before starting the compressor operation, install an oil
heater on the oil separator. In cold districts, install a band heater to the oil supply piping.