WIRING INSTALLATION OVERVIEW

NB

: Cables necessary for the installation of the system (not included) may vary according to the quantity 

and type of accessories and devices fitted.

Switch the POWER OFF before starting any wiring.

Fit a power cut switch to protect the electric plant against overcurrent.

The standard requires a separation of contacts of at least 3 mm in each pole(EN 60335-1).

The installation requires skills in the electrical and mechanical fields; it must only be performed by qualified

personnel able to release the declaration of conformity (type A) on the whole installation (Machine Directive

2006/42/CEE, attachment IIA).

The main electric plant shall comply with the oustanding regulation and shall be state of the art carried out.

The power supply lines to the motors, control unit and accessories must be separated in order to avoid possible

interferences that could generate system malfunctions.

The electric cable coming out of the actuator must not be stretched but make a wide downward curve to

avoid the backflow of water inside the actuator itself (see the picture above).

B

 

Operator 

Control unit

C

 

 

D

E

 

F

 

RX photocell

 

TX photocell

  

Antenna  

Radio receiver

 

ELENCO CAVI PER I VARI DISPOSITIVI

A

 

G

 

pic.

 B

4

rev01_22

pic.

 

A

3 x 1,5 mm² + Terra

2 x 1,5 mm² + Terra

4 x 0,5 mm²

 

2 x 0,5 mm²

  

2 x 0,5 mm²

 

230V/115V

2 x 0,5 mm²

 

2 x 0,5 mm² 

RG58

  

24V

2 x 0,5 mm²

 

2 x 0,5 mm² 

4 x 0,5 mm²

 

2 x 0,5 mm²

  

RG58

  

2 x 0,5 mm²

 

2 x 1,5 mm²

2 x 1,5 mm² + Terra

Summary of Contents for MYASTER 3 NEW

Page 1: ...01_22 Installation manual MYASTER NEW Automation for swing gates...

Page 2: ......

Page 3: ...3 3 3 4 Tools and materials not included Wiring Installing the operator 4 MANUAL RELEASE page 12 2 1 2 2 2 3 Technical data Operator dimensions page page page page page page page page page page page...

Page 4: ...against overcurrent Make sure the area is clear from flammable gases and or electromagnetic interferences it could lead to very dangerous injuries Switch the power and batteries OFF before any operat...

Page 5: ...00 110 22 200 3 50 40 230V 50Hz 1 7 280 8 150 2800 44 1400 120 32 250 4 00 40 3 INSTALLATION 3 1 PRELIMINARY CHECKS Before proceeding to installation it is necessary to double check the good condition...

Page 6: ...3 rev01_22 3 2 TOOLS AND MATERIALS NOT INCLUDED brick 18mm concrete 15mm inox alu tubular stainless steel PILLARS AND WALLS LEAF stainless steel alu wood 3 3 3 3 3 3 3 3 2 2 2 2...

Page 7: ...e 2006 42 CEE attachment IIA The main electric plant shall comply with the oustanding regulation and shall be state of the art carried out The power supply lines to the motors control unit and accesso...

Page 8: ...gate is particularly light fit the operator as closer as possible to gate centerline 3 4 2 PILLAR QUOTES The ideal approach is to fix the brackets complying with the measures A and B as indicated in t...

Page 9: ...opening angles without having to replace the existing ones MYASTER 6 NEW 90 D 275 250 225 200 175 150 125 100 75 A 210 240 280 275 300 300 330 370 410 B 335 330 305 310 285 290 265 240 215 Bracket 80...

Page 10: ...te opening outward picture F G H 5 mm 5 mm 5 mm 30 mm pic F pic G pic H MYASTER 3 NEW MYASTER 4 NEW MYASTER 5 NEW MYASTER 6 NEW A 115 115 115 115 B 220 200 200 200 Distance from pillar 5 5 5 5 Bracket...

Page 11: ...the bracket following the below procedure Linea di taglio 30 12 mm pic L Remove screw from plastic cap picture L A Fit the bracket to the motor picture L Fit the pin picture M Put the cap back and sc...

Page 12: ...acket in the motor and fit the pin picture Q Mount the arm of the motor onto the gate Ensure the arm is perfectly straight Check the manual opening of the leaf before definitively fixing the bracket t...

Page 13: ...e outstanding regulations ATTENTION The electric plant must be protected by a ground system in accordance to the current safety regulations Do not let the motor wire stretch during opening and closing...

Page 14: ...hown in picture V The operator is now unlocked manually open and close the gate Put the gate to closing position lock the operator turning the release key 180 clockwise Reposition the plastic cap as s...

Page 15: ...indirect damages resulting from the use or inability to use PROTECO products Any return without authorization number will be rejected The shipment of the returned product and the related costs are th...

Page 16: ...with other machinery to crate a machine under provisions of 2006 42 EC Machinery Directive It complies with the essential requirements of EEC Directives 2011 65 CE RoHS 2 2015 863 UE RoHS 3 2014 35 UE...

Page 17: ...Via Neive 77 12050 CASTAGNITO CN ITALY Tel 39 0173 210132 mygateautomation com info mygateautomation com...

Reviews: