Initial Energization
50
Initial Energization
Let’s energize the myPV ClearSky™ Interconnection for the first time, and walk through
the commissioning process to ensure everything is working properly.
Safety First!
This procedure is written to follow the conditions set by the prior section of this manual,
If you have not yet performed the Pre-Energization Checks, or have taken any actions
that altered the as-left conditions of the myPV ClearSky set forth at the completion of
the Pre-Energization Checks, we strongly recommend performing the Pre-Energization
Checks before proceeding.
The following steps will require authorized and qualified commission staff to CLOSE /
ENERGIZE individual medium voltage phases from the interconnection. Appropriate
personal protective equipment (PPE), electrically rated tools, and knowledge of the
energization process are required perform the energization process.
Improper PPE, tools, and/or knowledge will result in staff being exposed to the
full interconnection voltage and could result in injury and/or death.
The following steps should only be conducted by authorized and qualified commission
staff.
Preparing to Energize
Prior to allowing interconnection voltage to the myPV ClearSky or any portion of the
facility’s newly installed conductors or equipment, it is strongly recommended that the
following steps be taken to minimize unsafe conditions to staff and equipment:
1. All of the myPV ClearSky’s MV Termination Cabinet and Control Cabinet doors
should be closed and secured / LOTO’d
Summary of Contents for ClearSky
Page 1: ...myPV ClearSky User Manual 1 myPV ClearSky User Manual ...
Page 12: ...Resources 12 ...
Page 14: ...Resources 14 ...
Page 19: ...Resources 19 ...
Page 20: ...Resources 20 ...
Page 48: ...Pre Energization Checks 48 Control Panel Verification Locations ...
Page 55: ...Initial Energization 55 ...
Page 63: ...Operational Testing 63 The myPV ClearSky may be left in this condition indefinitely ...
Page 68: ...Spare Parts 68 ...
Page 69: ...Spare Parts 69 ...