Setting and connection
Important:
Activities described in this section must be performed by qualified personnel only.
If you use the machine for processing small pieces, you must fix it to a level surface by means
of the holes at the bottom of the stand (Fig. 4.1.1).
If you use the machine for processing large pieces, you must place it on the work piece, on
which it will move itself. When approaching the material and leaving the work piece at the
end, it is advisable to suspend the machine on the belt, as illustrated in Fig. 4.1.1.
During electrical installation, proceed as follows:
- Check the frequency and voltage values on the motor identification label;
- Connect the electrical supply cable end to a plug according to your local power supply
network.
Checking before use
Important:
Never start the UZ 15 Rapid without carrying out the checks described in this section.
Before starting the machine, check whether it is in working order by means of the following
checks and inspections in order to ensure the highest possible efficiency and to meet safety
regulations:
- Check whether there are no loose screws or other parts.
- Make sure that all electrical connections are correct and the electrical cable is fixed in place
with a cable gland.
- To start the machine, proceed as follows:
Release the red emergency locking button
(position B, Fig. 2.4.1).
Start the motor with green switch. The cutter must rotate clockwise.