1400 Fold Door System
www.NabcoEntrances.com
Part #15-9324
Rev. 11-26-14
3-11
Install Frame
installing into the opening.
Note:
Do not overtighten anchors to prevent deforming Jamb tubes.
3.c.a:
Secure Jamb Tubes to Rough Opening
Figure
3-6
Anchor Placement
DN 0832
36” max
48” max
48” max
Y
Y
Y
Y
Y
Y
5. Lift to position assembled Frame into the rough opening.
a. Ensure the Panic Catch magnets are toward the Interior side of Building.
b. Ensure the Weathering Strips are toward the Exterior side of Building.
6. Plumb Jamb tubes in both planes to ensure the rough opening allows a 1/4 inch clearance.
Please see Figure 3-7.
a. Shim back of Jamb as required.
7. Plumb the Header at the top to ensure the rough opening allows a 1/4 inch clearance.
a. Shim top of Header or Transom Horizontal as required.
Figure
3-7
Shim and Plumb Frame
1/4” Shim and plumb
for proper clearance
DN0831
Jamb Tube
Header
1/4” Shim and plumb
for proper clearance
8. Secure Jamb Tubes to Rough Opening accordingly. Please see Figure 3-8.
Standard Fold Door
• Use 1/4 inch diameter anchors with a minimum of 3 per Jamb tube, maximum is
48 inches on center. Drill 1/4 inch diameter holes in the face of Jamb Tube and then
countersink each hole. Please see Figure 3-6.
Hurricane Fold Door
• Screw in anchors to secure the Frame (per manufacturer’s certi ication document(s).
Figure
3-8
Secure Jamb Tubes to Rough Opening
DN 0658
SLICK JAMB
1/4” Anchor
1/4” Anchor Hole(s)