Rev. 9-24-14
Part #15-10683
GT 710-8710 Swing Door System Low Energy Operator
Install the Header
3-9
3.►
Measure 1 inch from the End Cap of Header towards the center. Mark a Vertical Line.
4.►
Measure at least 1/2 inch from the bottom of Header towards the top. Mark a Horizontal Line
across the Vertical line. This is the center of the first screw hole. Drill 1/4 inch screw hole.
5.►Mark (1) more Horizontal line across the Vertical line directly above the first screw hole. This is
the center of the second screw hole. Drill 1/4 inch screw hole.
a. It may be necessary to install a Shim behind the Header if mounting the Header to a wall.
6.►
Go to the Strike side of Header. Repeat steps 3 thru 5.
DN 1086
Pivot side of Header
1/4” Screw holes
1”
1”
Figure 3-2
Drill 1/4” Screw holes on both sides of Header
Section 3c: Prepare the Door Frame
Note: The following instructions are for typical Metal Doors and Frame Profile. It is recommended to use
lag bolts.
Note: If the Door Frame is not properly reinforced nor anchored to the building surface, and/or is hollow,
reinforce the Door Frame with 1/4-20 blind rivnuts (not provided by NABCO).
Note: If the Door Frame is not Metal, ensure the Door Frame being used is of equal strength.
1.►
Go to the Pivot Side of Swing door.
2.►
Measure up from the Bottom edge of the Top door frame:
X
GT 710: 1/8 inch
X
GT 8710: 1-1/8 inch.
3.►
Mark a Horizontal Line on the face of Top door frame, at both ends. Please see
DN 1109
Mark Measurement
across Top door frame
1/8”
(GT 710)
Top of Door
1-1/8”
(GT 8710)
Figure 3-3
Measure from the Top of Swing door to the Top Door Frame
4.►
Lift the Header up against the Top door frame until the bottom edge of Header is butted up
against the Horizontal Line, at both ends. Please see
.
5.►
To ensure proper operation of the Swing Arm:
X
For a Door Jamb that is 1-3/4 inches wide, position the Pivot side of Header so it is flush to
the outside edge of the Pivot Door Jamb.
X
For a Door Jamb that is wider than 1-3/4 inches, measure from the inner edge of the Pivot
Door Jamb to the center. Mark a vertical line at the 1-3/4 inch measurement. The Pivot side
of Header must butt against the 1-3/4 inch mark.