background image

Page 9 

 

4.

 

While using the factory mockup photos as a guide, trace through the RF 
schematic for the ATU system, starting at the RF input, and working through to 
the RF output.  As the components are identified in the RF schematic, the 
corresponding location of the component should be identified in the component 
layout drawing, and also observed in the corresponding photo(s). 

 
 

5.

 

During the actual installation of the components, which is covered in the 
following sections, the factory mockup photos should be referred to as needed for 
clarification.

 

D.  Installation of Floor-Mounted RF components 

 

1.

 

Refer again to the ATU floor layout drawing, showing the correct placement of all 
the RF components.   

 
2.

 

Make sure all of the mounting holes were drilled to the correct depth for 
anchoring the floor-mounted components, and that all the holes have been cleared 
of debris using the vacuum cleaner.   

 

3.

 

When all the holes have been drilled and vacuumed, install the hardware anchors 
into the holes in the concrete for each component panel. To ensure that all of the 
holes have been included, do this for only one component panel at a time. 

 

4.

 

Find all the floor-mounted component panels, as labeled on the drawing. Make 
sure all insulators and hardware are securely mounted on each component panel. 
Install each component panel as shown in the ATU floor layout drawing.  Make 
sure each component is oriented in the correct direction (refer to photos as 
needed).  

 

5.

 

Note:  Do not install any of the capacitors yet.  Only install the component 
panels at this time.  The capacitors will be mounted on these panels in a later 
step.

 

 

6.

 

The correct orientation for each component may be determined by carefully 
examining the photographs from the factory mockup of the ATU.  The final 
verification of the correct position and orientation will be made when the 
interconnecting copper pipe sections are installed.  In order for the copper pipe 
sections to mate properly with the components, the components must be 
positioned and oriented correctly. 

 
 
 
 

Summary of Contents for NX100

Page 1: ...ove Road Hackett s Cove NS Canada B3Z 3J4 T 877 6 nautel 628835 or 1 902 823 2233 F 1 902 823 3183 info nautel com U S customers please contact Nautel Inc 201 Target Industrial Circle Bangor ME 04401...

Page 2: ......

Page 3: ...Page 1 INSTALLATION INSTRUCTIONS FOR RF EQUIPMENT TO BE INSTALLED IN TUNING HUT AT THE 1062 KHZ STATION AIR SITE PROJECT PASSIGHAT Kintronic Laboratories Inc Bristol TN...

Page 4: ...Building Measurements 4 Overview of Installation Steps 6 Detailed Installation Procedure 7 A Floor Layout Panels 7 B Critical Overview of Component Installation 8 C Installation of Floor Mounted RF co...

Page 5: ...on material used to construct the Tuning Houses 5 English sized Allen wrench set 6 English sized wrench set 7 Hammer 8 Drill capable of drilling concrete 9 Tin Snips 10 Screw Driver Set 11 Flux 12 Sil...

Page 6: ...s NOTE keep all capacitors in their respective protective boxes until it is time to install them per the instructions Arc Gap Assemblies Grounding Switch Assemblies Meters and meter toroids keep meter...

Page 7: ...input which will connect to the transmission line from the Transmitter Building and the RF output which provides the interface to the Tower Measure the size of each opening and make measurements need...

Page 8: ...as each panel is removed 5 Become familiar with the pictures showing the factory mock up of the ATU and review these pictures against the RF schematic and the Component Layout drawing 6 Starting with...

Page 9: ...moved from the floor leaving only the Hardboard template 3 After the Hardboard layout pattern is fully assembled and secured pre drill all the marked hole locations for each panel with a 5 16 nominal...

Page 10: ...es of the components mounted on their respective component panels as well as the identifying labels that are used on all components and all relevant drawings An example photo noting typical ATU compon...

Page 11: ...es have been drilled and vacuumed install the hardware anchors into the holes in the concrete for each component panel To ensure that all of the holes have been included do this for only one component...

Page 12: ...d the component numbers engraved tag on panel match correctly Make sure all the connections are tight 3 Many of the pipe sections are connected together through the use of splitters The splitters are...

Page 13: ...ve a large clearance hole in the center The end of the capacitor with the adjustment knob must mount on this plate so that the knob passes down through this clearance hole Refer carefully to the facto...

Page 14: ...le can then be routed and secured properly Note that the cable must remain tight against the copper wall floor or in grounded conduit for protection 4 Mount the meters in the correct hole marked by th...

Page 15: ...Page 13...

Page 16: ...Page 14...

Page 17: ......

Page 18: ...DWG NO REV REF DWG DATE DRAWN SCALE APPROVED DESIGNED KINTRONIC LABORATORIES INC BLUFF CITY TN JOB NO COPYRIGHT KINTRONIC LABORATORIES INC...

Page 19: ...KINTRONIC LABORATORIES INC BLUFF CITY TN JOB NO DWG NO REV REF DWG DATE DRAWN SCALE APPROVED DESIGNED COPYRIGHT KINTRONIC LABORATORIES INC...

Page 20: ......

Page 21: ......

Page 22: ...acuum Capacitor Jennings C5 A CFC 250AS 30 250 30 Fixed Vacuum Capacitor Jennings B CFC 250AS 30 250 30 Fixed Vacuum Capacitor Jennings C6 A CFC 250AS 30 250 30 Fixed Vacuum Capacitor Jennings B CFC 2...

Page 23: ......

Reviews: