Section 3
Assembly.
Fitting the burner unit.
1.
seal with fire rope or heat resistant gasket sealer to the boiler via the
square hole located on side of boiler (left or right depending on
requirement).
2.
mount the burner unit into flange and secure locking bolts
Fitting the feed screw.
1.
fit one end of the thermoplastic hose to the top of the inlet tube on the
burner unit, and the other end of the thermoplastic hose to the outlet of
the feed screw.
2.
mount the feed screw over the burner so the pellets can fall into the
burner effortlessly. The more the feed screw is mounted at an incline, the
less pellets it releases.
- adjust the control system according to the angle of incline. (see section 5,
operating the burner)
3.
ensure the thermoplastic hose is angled enough so the pellets end up in
the burner, shorten the hose if needed.
Page 5
Summary of Contents for Scotte 16kw
Page 1: ...Scotte Opop Installation and operating Manual 16 24 30kw NORDIC BIO ENERGY LTD Pellets Systems...
Page 5: ...Dimensions of burner and wiring diagram Page 4...
Page 16: ...Page 14...
Page 18: ......
Page 19: ...Quick Start 16kw NBE Pellets Systems Estimating Table...
Page 20: ...Quick Start NBE Pellets Systems Estimating Table...
Page 21: ......
Page 22: ...Quick Start NBE Pellets Systems Estimating Table...