Installing the Main Equipment Cabinet
22
◆
Installation
DSX-80/160 Hardware Manual
Installing the Main Equipment Cabinet
Planning the Installation
Before installing the common equipment, you should mount a Main Distribution Frame (MDF) plywood back-
board in a centrally located spot. A 1/2 sheet of plywood (4’ x 4’) should be adequate for a DSX-80 4-Slot
KSU. A full sheet of plywood (8’ x 4’) should be adequate for a DSX160 cabinet. Be sure to mount the back-
board using suitable fasteners, taking care to adhere to standard installation practices and local codes. See
Fig-
ure 1: Installation Layout, DSX-80
below and
Figure 2: Installation Layout, DSX-160
(page 23) for more.
The Main Equipment Cabinet requires a three-prong, dedicated 110 VAC 60 Hz circuit (NEMA 5-15 recep-
tacle). The AC receptacle must be within 7 feet of the cabinet’s lower left corner.
Normally, you install the extension and line blocks to the right of the cabinet. Telco should also install the
RJ21X to the right of the cabinet
.
Figure 1: Installation Layout, DSX-80
Important
Local codes may prohibit you from installing extensions,
trunks and optional equipment in the same blocks.
1093096 - 14
Plywood backboard
Dedicated
AC Outlet
Surge
Protector
To earth
ground
To telco
ground
Station
Block
Station
Block
Line
Block
4'
4'
Note:
The system will respond to telco ring signal in the
range of 40-130 VAC @ 20 Hz.