4.1.6
Replacing Memory Backup
The battery on the CPUII( )-U10 ETU is used to retain the Clock/
Calendar and Last Number Redial (LNR) buffers for each station
when the CPU encounters a power loss. When the battery is fully
charged, the settings are retained for approximately three years.
The Lithium (CR2032) battery should be replaced every two years.
The system programmed memory (Customer Database) is stored in
Non-Volatile Memory and can only be erased by a First Initialization.
1.
Turn off the KSU power.
2.
Remove the CPUII( )-U10 ETU from the KSU.
3.
Remove the battery from connector CN6.
4.
Install new CR2032 battery in CN6.
5.
Install the CPUII( )-U10 ETU in the KSU.
6.
Turn on the KSU power.
4.1.7
DSPII-U10 Daughter Board
Systems that use VRS or In-Mail require the daughter board. VRS
and In-Mail are provided on a Compact Flash card that plugs into the
daughter board. The DSPDBU plugs into the CN7 connector on the
CPUII( )-U10 ETU.
On
Blinking
Blinking
Off
On
Finish format (SRAM,
Flash)
Blinking
Off
Off
Off
On
DRAM error
Blinking
Off
Off
On
On
FPGA version error
Blinking
Off
On
Off
On
SRAM error
Blinking
Off
On
On
On
Flash memory boot error
Blinking
On
On
On
On
Flash memory data error
Blinking
Blinking
Blinking
Blinking
On
System Program reading
error
Blinking
Off
Off
Off
On
System starting up
Table 6-3 CPUII( )-U10 Status
LED Indication
Status
LED5
LED4
LED3
LED2
LED1
Summary of Contents for ELECTRA ELITE IPK II
Page 2: ......
Page 3: ...SYSTEM HARDWARE MANUAL INT 1076 IPK II DOCUMENT REVISION 3 VERSION 2000...
Page 4: ......
Page 6: ......
Page 10: ...THIS PAGE INTENTIONALLY LEFT BLANK...
Page 641: ...SYSTEM HARDWARE MANUAL NECUnified Solutions Inc Document Revision 3...
Page 642: ......