Upgrading Your Server 9-29
Removal
To remove the CPU, prepare the removal referring to steps 1 and 6 in the installation procedure and
do the reverse procedure of steps 12 to 8.
IMPORTANT:
Do not remove any CPU unless it is failed.
After the operation, heat may make the cool seat at the bottom of
the heat sink adhere to the CPU. To remove the heat sink from the
CPU, first turn the heat sink to the left and right lightly to make sure
that the heat sink can be apart from the CPU. Removing the heat
sink with it adhering to the CPU may cause the CPU and/or socket
to be defected.
Do the following procedure if a CPU is removed (or replaced).
1.
Start SETUP to select menus "Main" – "Processor Settings" – "Processor Retest" in the
order to clear the error information on the removed CPU (see Chapter 4).
When a CPU is replaced, select menus "Main" – "Processor Settings" to confirm that the
ID and L2 Cache of the additional CPU are defined normally (see Chapter 4).
2.
Set "Reset Configuration Data" on the Advanced menu to "Yes."
This is required to update the hardware configuration information. See Chapter 4 for
details.
Summary of Contents for Express5800/120Rh-2
Page 142: ...4 46 Configuring Your Server This page is intentionally left blank ...
Page 236: ...7 12 Maintenance This page is intentionally left blank ...
Page 320: ...9 46 Upgrading Your Server Pin Red Pin Red N8103 80F N8103 81F ...
Page 336: ...9 62 Upgrading Your Server This page is intentionally left blank ...
Page 338: ...A 2 Specifications This page is intentionally left blank ...
Page 346: ...C 2 IRQ This page is intentionally left blank ...
Page 406: ...G 4 Product Configuration Record Table This page is intentionally left blank ...