Slide two slide rails out from the rack until they were locked. And then with three or 
more persons assisting you, lift the server and align the inner rails attached to the 
both side of the server with the extended rails. 

(8)

 

Insert the inner rails into the extended slide rails and push the server into the rack 
until it stops. 

(9)

 

Carefully press down the release levers on the inner rails to release the locks and slide 
the server all the way into the rack. 

(10)

 

To check that the server slides in and out of the rack, grasp the two handles on the 
front of the server slowly pull the server out and push it back in. 

(11)

 

Tighten the four captive thumbscrews to secure the server to the rack. 

 

 

 

Note sufficiently that your fingers may not be caught between a 
rail and other  mechanical parts or cut by a rail at installation or 
removal of the server from the rack. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

 

 

 

?

 

Do not connect any cables before attaching the cable arm. 

?

 

Secure four captive thumbscrews when mounting the server to the rack. 

 

Captive thumbscrews

 

Front Cover 

 

Release Lever 

Summary of Contents for N8143-56E

Page 1: ...rrectly and or personal injury or damages of surrounding servers to occur More than two persons are required to carry or install the rack Failure to follow this instruction may cause the rack to fall to result in personal injury and or breakage of surrounding servers Read this document and the manual of the NEC Express server to understand installation method before installing this product to the ...

Page 2: ...red for installing the server on a 19 inch rack step by step Step 1 Unpacking The rack conversion kit contains the following components Make sure that everything listed below are inside and no damage is observed after unpacking 19 18 17 5 6 1 2 3 7 8 9 10 11 12 13 14 15 16 20 21 22 4 ...

Page 3: ...xed HDD model 11 HDD Cover 2 1 For Hot Plug ATA HDD model 12 Template 1 13 Model Name Label 1 120Lg 120Ef 用 14 Model Name Label 1 120Lh 120Lg 用 15 Icon Label 1 16 Washer 8 For fixing the slide rail assembly 17 Screw A 8 M4 Bind head screws color Gold 18 Screw B 10 M5 Bind head screws 19 Screw C 8 6 32UNC pan head screws color silver 20 Screw D 11 M4 pan head screws with Washer color Gold 21 Cable ...

Page 4: ... out Then slide the front bezel to remove it from the other hinge pin and remove the front bezel 2 Remove the bezel hinge four screws 3 Remove five nylon rivets from the top cover 4 Remove four feet from the bottom chassis Total eight screws 5 Fix the device covers together with the dummy covers which were installed to blank bays in the chassis Front Bezel Foot Hinge Pin Nylon Rivet Bezel Hinge Fr...

Page 5: ...ts model Fixed HDD 4slots model Fix HDD cover 1 with four screws D Hot Plug ATA HDD 4slots model Fix HDD cover 2 with two screws D 7 Fix four foot covers with four screws C to the bottom of server 8 Fix the front cover with four screws C to the front of server Foot Cover Front Cover Front Cover HDD Cover 1 HDD Cover 2 Front Cover ...

Page 6: ...rail 2 Fix the inner rail with eight screws A to both sides of the server 3 Place the template in the desired location of the rack and attach four core nuts that come with the rack assembly to the mount flange in the rack Release Lever Slide Rail Assembly Outer Rail Inner Rail Core nut positions Slide Rail Front side Core nut positions Cable Arm position Slide Rail Back side ...

Page 7: ... 5 Place slide rail assemblies to the mounting flanges of the rack Attach the washer to the screw B and then fix both sides of slide rails with eight screws B Refer to the template for the position 6 Tighten six screws that were loosened in 4 Front side Back side Rear Mounting Outer Rail Slide Rail Assembly Screws for Rear Mounting bracket ...

Page 8: ...nd slide the server all the way into the rack 10 To check that the server slides in and out of the rack grasp the two handles on the front of the server slowly pull the server out and push it back in 11 Tighten the four captive thumbscrews to secure the server to the rack Note sufficiently that your fingers may not be caught between a rail and other mechanical parts or cut by a rail at installatio...

Page 9: ...D to the back of the server 2 When the distance between the front mounting flange and the rear mounting flange is about 743mm align one end of the cable arm with the outside of the core nuts installed to the rear of the rack frame and secure it with the two screws B Server Arm Bracket ...

Page 10: ...le arm and the arm bracket and then fix the cable arm with two screws D to the arm bracket that fixed in step 1 Distance between the front mounting flange and the rear mounting flange 700_742mm Cable Arm Attach the cable arm to the arm support to shorten this distance as much as possible Cable Arm Arm Support 2 Arm Support 1 Cable Arm Arm Bracket Small Hole Distance between the front mounting flan...

Page 11: ...plied to the cable arm by rotating it 7 Attach cables to the server according to the manual of the server 8 Bundle cables to the cable arm by the repeat ties Attach cables and repeat ties not to contact the slide rails and neighboring units and the rack Tie cables slackly between the cable arm and the server to avoid of excess force to be added by pulling out the server and pushing it back in Atta...

Page 12: ...hange of the power supply unit Check to see that no excess force is applied to cables by rotating it If the excess force is applied to cables tie again cables more slackly and check to see that no excess force is applied to cables and check the cable does not touch slide rails neighboring units and the rack 10 Fix the arm stopper with a screw D to the cable arm Arm Stopper Cable Arm ...

Page 13: ...n label corresponding to each model on the front cover Icon Label Model Name Label 10mm 10mm Model Name Label Icon For NEC Express5800 120Ef For NEC Express5800 120Lg For NEC Express5800 120Lg For NEC Express5800 120Lh For NEC Express5800 120Ef For NEC Express5800 120Eg For NEC Express5800 120Lh For NEC Express5800 120Eg ...

Page 14: ... describes the procedures for rotating the cable arm to backside 1 Loosen the screw D and slide the arm stopper to upside and then remove the arm stopper 2 Rotate the cable arm to backside 3 Attach remove cables and power supply units 4 Rotate the cable arm to previous position 5 Attach the arm stopper and then tighten the screw D that was loosened in 1 Screw D Arm Stopper Cable Arm ...

Page 15: ...Loosen four captive thumbscrews on the front of the server 2 Grasp the two handles on the front of the server slowly pull it out until it stops locks by the release levers 3 Do the maintenance of internal components according to the manual of the server 4 Carefully press down the release levers on the inner rails to release the locks and slide the server all the way into the rack 5 Grasp the two h...