CHAPTER 2 INSTALLATION
Connection of DC Power Cable
NEAX2000 IVS
2
Installation Procedure Manual
Page 86
ND-70928 (E), Issue 1.0
(3)
When you need a –48V DC power supply installed for a Cell Station (Zone Transceiver) in
WCS system, do the following procedure. If not, skip this procedure and go to item (4) on
Page 88
.
STEP 1: Attach four screws preliminary to the PZ-PW122 card.
STEP 2: Mount the PZ-PW122 card into the PIM which accommodates the CSI cards, and fas-
ten the screws.
NOTE:
Screws are attached to the PZ-PW122 card.
Figure 2-31 Mounting PZ-PW122 into PIM
PIM
PZ-PW122