CHAPTER 2 INSTALLATION
Procedure
NEAX2000 IVS
2
Installation Procedure Manual
ND-70928 (E), Issue 1.0
Page 45
PROCEDURE
This flowchart explains the procedures for installing the PBX system. Follow the procedures in
Figure 2-2
.
Figure 2-2 Procedure Flowchart (1 of 2)
START
UNPACKING
INSTALLATION
OF
MAIN EQUIPMENT
BATTERY
CONNECTION
TERMINATION OF
CABLES ON MDF
SUPPLY VOLTAGE CHECK
AND
HEAT RUN TEST
CABLE RUNNING
TO MDF
INSTALLATION
OF
PERIPHERAL EQUIPMENT
A
POWER CABLE
CONNECTION
SWITCH SETTINGS
OF
CIRCUIT CARDS
REFER TO
CHAPTER 3
.
Page 49
Page 54
Page 83
Page 90
Page 94
Page 102
Page 109
Page 128
WIRING AC CABLE
TO
TERMINALS
Page 50