CHAPTER 2 INSTALLATION
Wall Mounting Installation
NEAX2000 IVS
2
Installation Procedure Manual
Page 72
ND-70928 (E), Issue 1.0
Wall Mounting Installation
• Check the site for installing the PBX with the work drawing to verify that
the required floor space is ensured and that service entrances and ducts
for trunk/extension cables, power cables and grounding conductors
have been properly worked at correct positions.
See
Figure 2-7
and
Figure 2-8
.
• Detach the front cover of each PIM. See “Detaching FRONT COVER”
on
Page 60
.
• Mark hole positions for installation of the PBX main equipment. See
Figure 2-19
.
• Secure the HANGER ASSEM to the wall.
• Hang the PIM to the HANGER ASSEM. See
Figure 2-20
.
NOTE:
The BATTM cannot be installed on the wall.
• After hanging each PIM to the respective HANGER ASSEMs, connect
PIMs using screws. See “Connection of PIMs” on
Page 66
.
• Carefully review every step above to ensure that all necessary screws
are properly placed and tightened.
Start
Checkup
before installation
Marking
Installation of PIM
Multiple-PIM
Checking
Detaching
Front Cover
End
Configuration