NEAX2000
IVS
2
ISDN System Manual
Page 196
ND-70919 (E), Issue 1.0
CHAPTER 5 OPERATION TEST
PLO Operation Test
Clock Signal Synchronization Test
This test checks to see if the PLO keeps synchronizing with the external clock signals, when the
external clock signals from network has input again after it has stopped once. Do the following
procedure using “In Service” transmission lines.
(1)
When providing one clock supply route
STEP 1: On the DTI0/PRT0/BRT0 card extracting clock signals, set the switches as follows to
stop the external clock signal input:
• 30DTI0 card:
SW-1 and SW-2 to OFF
• PRT0/24DTI0 card:
SW0-1 and SW0-2 to OFF
• BRT0 card:
SW0-2 and SW0-3 to OFF
• 2BRT0 card:
SW11-2 and SW11-3 to OFF
– The CLK lamp on the MP card goes out.
STEP 2: Originate an outgoing call via trunk.
STEP 3: After an outgoing connection via trunk has been established, confirm interoffice
synchronization and speech quality as follows:
• On the DTMF telephone set, keep pressing any dial button.
• Check to see if noise periodically occurs on the DTMF signals coming from the
calling station in the opposite office.
• Do the above test again in the opposite direction.
STEP 4: On the DTI0/PRT0/BRT0 card, restore the switches as the state before testing to input
the external clock signals:
• 30DTI0 card:
SW-1 to ON, SW-2 to OFF
• PRT0/24DTI0 card:
SW0-1 to ON, SW0-2 to OFF
• BRT0 card:
SW0-2 to ON, SW0-3 to ON
• 2BRT0 card:
SW11-2 to ON, SW11-3 to ON
– The CLK lamp on the MP card lights.
STEP 5: Originate an outgoing call via trunks.
Summary of Contents for NEAX 2000IVS2
Page 1: ...ND 70919 E ISSUE 1 STOCK 151988 ISDN System Manual FEBRUARY 2000 NECAmerica Inc ...
Page 11: ...NEAX2000 IVS2 ISDN System Manual Page vi ND 70919 E Issue 1 0 This page is for your notes ...
Page 211: ...NEAX2000 IVS2 ISDN System Manual Page 200 ND 70919 E Issue 1 0 This page is for your notes ...