Issue 4.1
UNIVERGE SV8100
3 - 62
Installing the SV8100 Chassis
3.2
Installing the External Batteries
An optional (locally procured), external battery source can be used to provide
power in the event of a power failure.
CHS LARGE BATT BOX (Backup time = Three Hours for 30 Terminals)
3.2.1
Floor Mounting the CHS LARGE BATT BOX
1.
Use the template shown in
Figure 3-78 Floor Mount Spacing
Guide on page 3-63
for required spacing before drilling holes
for 0.39” (10mm) anchor bolts (locally procured).
Table 3-2 CHS LARGE BATT BOX Capacity
Configuration
Battery Capacity
(Number of Batteries)
Number of
CHS LARGE BATT
BOX
SV8100
2U x 1
21AH (=3 sets of [2x12V-7AH])
1
2U x 2
42AH (=6 sets of [2x12V-7AH])
2
2U x 3
63AH (=9 sets of [2x12V-7AH])
3
2U x 4
84AH (=12 sets of [2x12V-7AH])
4
.
One CHS LARGE BATT BOX can be used for 4 x 2U chassis for approximately
45 minutes.
Because of injury from falling equipment, wall
mounting the CHS LARGE BATT BOX is not
recommended.
Mounting the CHS LARGE BATT BOX directly
on the floor is not recommended.
The CHS BASE UNIT
raises the height of the
CHS LARGE BATT BOX 120mm (4.72”).
When the CHS LARGE BATT BOX and
CHS2U are connected for long term use, the
CHS2U JOINT BRACKET KIT is used.
Summary of Contents for Univerge SV8100
Page 1: ...System Hardware Manual Issue 4 1 February 2011...
Page 2: ...THIS PAGE INTENTIONALLY LEFT BLANK...
Page 36: ...Issue 4 1 UNIVERGE SV8100 1 14 Introduction to SV8100...
Page 68: ...Issue 4 1 UNIVERGE SV8100 2 32 SV8100 System Specifications...
Page 99: ...UNIVERGE SV8100 Issue 4 1 System Hardware Manual 3 31 Figure 3 34 Install Screws Option 2...
Page 148: ...Issue 4 1 UNIVERGE SV8100 3 80 Installing the SV8100 Chassis...
Page 247: ...UNIVERGE SV8100 Issue 4 1 System Hardware Manual 4 99 Figure 4 34 Control Signal Connection...
Page 258: ...Issue 4 1 UNIVERGE SV8100 4 110 Installing the SV8100 Blades NOTES...
Page 418: ...Issue 4 1 UNIVERGE SV8100 6 64 Installing SV8100 Optional Equipment...