Issue 4.1
UNIVERGE SV8100
4 - 10
Installing the SV8100 Blades
2.6.2
Performing a Hot Start
The section describes how to load system software from flash
memory and customer data from RAM memory.
1.
Turn the system power off.
2.
After it has powered down, press the button again to power the
system back up. Wait approximately two minutes.
3.
When the system has completed reloading the software, the
Status LED is flashing on the CD-CP00.
2.6.3
Resetting the System
This section describes the process of resetting a system that is
running. Observe the important information listed in below.
To reset the system:
2.6.3.1
Initial Programming
The system can be programmed using three methods:
Programming using a multiline terminal
PC Programming
Web Programming
To program using a multiline terminal, enter programming
mode:
1. Go to any working display telephone.
2.
Do not
lift the handset.
.
In a newly installed system, use extension (port 1).
3. Press
Speaker
.
4.
#
*
#
* .
5. Dial the system pa
Transfer
.
Password
System software is loaded from flash memory and the
customer data is loaded from RAM memory.
IMPORTANT CONSIDERATIONS
Summary of Contents for Univerge SV8100
Page 1: ...System Hardware Manual Issue 4 1 February 2011...
Page 2: ...THIS PAGE INTENTIONALLY LEFT BLANK...
Page 36: ...Issue 4 1 UNIVERGE SV8100 1 14 Introduction to SV8100...
Page 68: ...Issue 4 1 UNIVERGE SV8100 2 32 SV8100 System Specifications...
Page 99: ...UNIVERGE SV8100 Issue 4 1 System Hardware Manual 3 31 Figure 3 34 Install Screws Option 2...
Page 148: ...Issue 4 1 UNIVERGE SV8100 3 80 Installing the SV8100 Chassis...
Page 247: ...UNIVERGE SV8100 Issue 4 1 System Hardware Manual 4 99 Figure 4 34 Control Signal Connection...
Page 258: ...Issue 4 1 UNIVERGE SV8100 4 110 Installing the SV8100 Blades NOTES...
Page 418: ...Issue 4 1 UNIVERGE SV8100 6 64 Installing SV8100 Optional Equipment...