Pre-Commissioning Checklist
Warning! This humidifier must be installed, operated and maintained in accordance with this manual.
Failure to do so could result in contamination that might cause Legionnaires’ disease, which can be fatal.
Complete the following Checklist before commencing commissioning.
1. Switch off AHU.
2. SK VAP Evaporative Module Installation.
Check that the Module has been installed level in all planes with secure
blankingplates to prevent air bypass. Check that there is sufficient access for evaporative matrix cassette removal during
maintenance. Ensure assembly is securely fixed, and that there is no visible damage. Check that the Module is installed
in a waterproof section.
3. SK VAP Control panel Installation.
Check that the SK VAP Control panel is mounted in a convenient dry location
and has been connected to the SK VAP Evaporative Module via the proper electrical cable. Check electrical
connections with reference to the wiring diagram in the manual.
4. Feed water Installation.
Ensure the water system in the building has been subject to a Risk Assessment. The
SK VAP system MUST be connected to a clean, potable mains water supply. It is the responsibility of the user to
ensure that the water system complies with local regulations and bylaws, particularly those for the control of Legionella
bacteria. The use of mains water fed tanks and reservoirs is only permitted as part of a managed water treatment
system. Check that the SK VAP Evaporative Module has a feed water supply in excess of 29 psi (2 bar) connected to the
supplied filling hose. Ensure that the PureFlo Ag+ system is installed. Check all joints and fittings for leaks.
5. Drain installation.
Check that the drain on the SK VAP Evaporative Module is connected to the main building drain.
Ensure that this drain pipe-work is trapped to a suitable level for the applicable working duct pressure, refer to the rele-
vant section of the manual. Check all joints and fittings.
6. Distribution Pipework.
Check all water distribution pipework between the pump assembly and the distribution
headers are securely fitted.
7. Electrical Power Supply.
Check that a 120Vac / 10A power supply is connected to the SK VAP Control panel. Check
that this power supply is isolated within 39” (1 m) of the SK VAP Control panel.
8. Optional Controls:
Check that appropriate controls connections have been made to the SK VAP Control panel. Refer
to the controls wiring section of the manual.
9. Module Water Tank.
Check that the SK VAP Evaporative Module water tank is free of any dirt and debris,
and is clean.
10. Flush Water Supply:
Check that the water supply has been flushed to prevent water stagnation and to clear any flux
or foreign matter. This must be done carefully without creating splashing or aerosols.
11. Pressure test:
Turn on water supply and check for leaks.
12. Health and Safety.
Take a water sample to ensure that supply meets the requirements below. The sample should be
tested using a dip slide to indicate the total number of coliforming units per ml (cfu/ml). Generally, levels of 1x10
3
cfu/ml
may be considered acceptable for this type of humidifier provided the species of bacteria and/or fungi involved are
themselves not considered to be harmful.
Summary of Contents for SK VAP
Page 4: ...4 Neptronic www neptronic com Evaporative Humidification Cooling System...
Page 17: ...17 Neptronic Evaporative Humidification Cooling System www neptronic com Wiring Diagram...
Page 18: ...18 Neptronic www neptronic com Evaporative Humidification Cooling System...
Page 19: ...19 Neptronic Evaporative Humidification Cooling System www neptronic com...
Page 20: ...20 Neptronic www neptronic com Evaporative Humidification Cooling System...
Page 21: ...21 Neptronic Evaporative Humidification Cooling System www neptronic com...
Page 22: ...22 Neptronic www neptronic com Evaporative Humidification Cooling System...
Page 34: ...34 Neptronic www neptronic com Evaporative Humidification Cooling System...
Page 35: ...35 Neptronic Evaporative Humidification Cooling System www neptronic com...