5.5.
Installation of humidifier with Space Distribution Unit (SDU)
18'’
(0,45 m)
78'’
(2 m)
Without
additional
ventilation
54'’ (1,35 m)
E
neptronic
SDU mounted on humidifier
(Illus. 26)
The SDU should be installed in an
environment where the air is relatively
clean. This will avoid the blower from
getting clough with dust.
The humidifier should be mounted such
that the SDU fan section is at least 2m
above the floor.
A minimum clearance of 0.45m from the
ceiling should be allocated to avoid
ceiling and wall condensation.
If additional ventilation is not present,
the fan should have a clearance from
the ceiling of at least 1.35m. Proper
ventilation must be observed to avoid
ceiling and wall condensation.
SDU remote installation:
The SDU can be in a different location
from the humidifier (remote SDU).
Please follow the piping
recommendations (section 5.2).
Mount the SDU to the wall on brackets
(not supplied), do not drill mounting
holes thru the cabinet of the SDU.
Connect the steam hose(s) to the
bottom inlet(s) of the SDU to the top of
the steam outlet(s) of the humidifier.
Secure the hose(s) with the supplied
hose clamp.
Connect the condensate hose to the
bottom of the SDU to an open drain.
Connect the electrical wires from the
SDU to the top of the humidifier. Field
wiring must conform to local codes.
The fan of the SDU will operate for a period
of four minutes after steam production has
stopped to prevent condensation.
Avoid any obstruction of the ventilation
openings on top of the SDU.
Maintenance of the SDU:
Clean the blower if there is an
accumulation of dust.
18'’
(0,45 m)
78'’
(2 m)
Field piping
(not supplied)
Without
additional
ventilation
54'’ (1,35 m)
4'’
(0.10m)
Field wiring
(by others)
2nd pipe
for SDU2 or SDU3
E
neptronic
SDU remote installation
(Illus. 27)