11. Start up procedure
We recommend to strictly following this start-up procedure in order to avoid any anomaly resulting from wrong
cleaning of the components.
In case of problem or discrepancy see section 14 – Trouble shouting guide.
1.
Make sure that mechanical, electric and plumbing connection are done and secured.
2.
Make sure that low voltage control circuit is done and correct.
3.
Turn on the water shut off valve (outside of the humidifier) and check that the drain connections are
connected to the main drain line of sufficient diameter.
4.
Turn on the power to the humidifier from the circuit breaker disconnect. The POWER indicator should go
on.
5.
Push the TEST button located on the main pc. Board. This pc. Board is located in the electrical
compartment.
6.
This will start up a pre-programmed start-up cycle. This start-up cycle will test functions of the humidifier
and will flush out any dirt in the humidifier and supply lines.
This cycle will last about 1 hour.
Note:
a) the front panel rocker switch will not affect the performance of the start-up cycle.
b) In the case of modulating humidifier, there must be a demand signal of at least 50% for the start-up
cycle to operate correctly.
c) To bypass at any time the start-up cycle and to proceed directly into normal operation, press the
RESET button located on the main pc. board.
7.
The front panel rocker switch may be left in the AUTO position during the start-up cycle. This will result in
normal operation of the humidifier as soon as the start-up cycle is finished.
8.
Your humidifier is now fully operational.