SKG3 Gas Fired Humidifier
Installation Instructions and User Manual
10
Installation Overview
All installation work must comply with local regulations.
All work related to the installation of the SKG3 Steam Humidifier MUST only be
performed by skilled and qualified technical personnel (e.g. qualified gas installer,
fitters, electricians, plumbers or technicians with appropriate training).
The customer is responsible for ensuring their suitability.
To install the SKG3 Steam Humidifier and its associated components, no special
tooling is required above that of a
fitter’s toolkit.
Installation
Method
Statement
Stage1: Unit Positioning and Mounting
Stage 2: Steam Distribution Installation
Stage 3: Gas Supply Connection
Stage 4: Water Supply Installation
Stage 5: Water Drain Connection
Stage 6: Combustion Air Installation
Stage 7: Flue Gas Venting Connection
Stage 8: Electrical Supply and Installation
Stage 9: Electrical Control Connections
Installation overview - Fig. 11
!
Stage 2
Stage 4
Stage 5
air
Stage 6
Stage 7
Stage 8
Stage 3
Stage 9
or
air
To drain
air
air
air
air
Stage 1