SKG4-E Gas Fired Humidifier
Installation Instructions and User Manual
Page | - 60 -
Start-up Procedure
Initial verification and start-up must be carried out by suitably qualified personnel.
It is strictly recommended to follow this start-up procedure in order to avoid any anomaly resulting
from inaccurate installation of the components.
Initial Verification
Clearance
1. Ensure that the humidifier cabinet is installed in a location in which
the humidifier can be serviced correctly.
Electrical
Supply
2. Verify that the power supply (voltage) conforms to the appliance
name plate on the side of the humidifier.
3. Confirm that 24Vac is present between terminals TB4 1&2 on the
control connection PCB. Remove the front top cover to get to this
PCB.
Water Supply
4. Ensure that water is supplied to the humidifier and that a shut-off
and a non-return valve are placed outside the humidifier.
5. With the water shutoff valve turned on, check that the drain
connections are connected to the main drain line with sufficient
diameter. Ensure that there are no apparent leaks.
6. Confirm that the drain piping is properly connected with a pitch of at
least 6.5mm per 300mm horizontal run.
Steam
7. Verify that the steam distributors are properly installed into the
ventilation duct.
8. Verify that the flexible steam hoses and rigid steam supply pipes
are shorter than 5 m in total, are properly sloped and have
condensation
“S” traps wherever required.
Gas Supply
9. Confirm that a proper regulator and gas test point have been
installed on the gas line to the humidifier.
10. Confirm that gas is supplied to the humidifier and that the shut-off
valve located outside the humidifier is closed. With the shut-off
valve is turned on, check for leaks, gas, smell or hissing sounds.
Flue Gas
Venting
11. Verify that the flue gas venting is as follows:
a) Ensure that a tee is installed with a drain trap for the flue gas
condensate.
b) Check that all connections are air tight.
c) Ensure that the total length of the flue gas venting pipe is no
longer than 30 meters.
d) Verify that an approved venting system has been used.
Note: Aluminum B vent is not acceptable
.
Controls
12. Ensure that the Airflow switch is properly installed and connected to
the printed circuit board. If an Airflow switch is not used, verify that
a jumper is connected between terminals TB3 1&2.
13. Ensure that the High limit duct humidistat is properly installed and
connected to the printed circuit board. Verify that the setpoint is
properly adjusted. If a High limit duct humidistat is not used, verify
that a jumper is connected between terminals TB3 1&3.
14. Ensure that the Interlock is properly connected to the printed circuit
board. If the Interlock is not used, verify that a jumper is connected
between terminals TB3 1&4.
15. If a room or duct humidistat is used, verify that it is correctly
installed and properly connected to the humidifier. Verify that the
setpoints are properly adjusted.
16. Turn the power on using the circuit breaker.
17. Confirm the control set-up of the humidifier and verify that the
setpoints are properly adjusted.
Summary of Contents for SKG4-E Series
Page 70: ...Notes ...
Page 71: ......