9.1. Installing the Rack Brackets
BEFORE REMOVING THE SERVER COVER, DISCONNECT ALL POWER. UN-
PLUG THE AC POWER CORD; DISCONNECT ALL PERIPHERIALS, AND ALL LAN
LINES.
When the server is to be installed into a rack, it is necessary to install two rack mount brackets on-
to the server chassis prior to installing the server into the rack. Follow the procedures below to in-
stall the rack mount brackets onto the server
Preparing for the Installation
• Review all the tasks required to install and configure the system
• Review the electrical requirements and power supply input voltage information
• Examine the system’s shipping kit contents and assemble the required tools for installation
• Review ESD requirements and take safety precautions
• Before installing the system into a rack, install any optional components into the system
• tabilize the rack before installing the system, if necessary
Use caution when removing the inner rail from the rail kit assembly. The rails can slide
out and cause personal injury or damage to the server.
Summary of Contents for Demos R130 M2
Page 1: ...Netberg Demos R130 M2 server...
Page 2: ...Netberg Demos R130 M2 server...
Page 11: ...Netberg Demos R130 M2 server xi 9 5 Aligning the Rails 222...
Page 14: ...1 Chapter 1 Netberg Demos R130 M2 server...
Page 31: ...Netberg Demos R130 M2 server 18 On HDD failure HDD Fault Amber Off No failure detected...
Page 32: ...19 Chapter 2 Installing hardware...
Page 57: ...Installing hardware 44 Figure 2 36 Installing the Air Duct...
Page 60: ...Installing hardware 47 Figure 2 40 Connecting the Fan Assembly Cables...
Page 143: ...130 Chapter 6 Server Management Software...
Page 169: ...156 Chapter 8 Web Graphical User Interface GUI for ESMS...
Page 230: ...217 Chapter 9 Rail Kit Assembly...
Page 236: ...223 Chapter 10 Troubleshooting...