Apply silicone to 
join as indicated.

Seal the join 

between wall profile 

and frame. 150mm 
up from base on 
both sides.

Summary of Contents for Rhine Pivot Series

Page 1: ...508 639 5463 if any damage has occurred or a defect identified within 8 hours of receiving the goods so this can be rectified 3 Do not proceed with installation until resolved Important May 2020 INCLUDES 2 SIDED SHOWERS AND 3 SIDED ALCOVE DOORS Rhine Pivot Low Profile Tray Series INSTRUCTION MANUAL ...

Page 2: ...s panel will cause it to explode without warning Unpack all glass assemblies Stand glass on soft packaging on the floor and against a wall Care must be taken not to strike any edge or corner against a hard surface as this will chip and destroy the glass panel Installation Glass panels and assemblies are heavy Two man lifting is recommend for handling and installation Determine positioning of wirin...

Page 3: ...l and flat Walls also must also be plumb and flat Two walls multiply errors and limit the potential to fit the acrylic liner and shower screen PREPARATION CHECKLIST DOOR SET TRAY SIZE CORNER POST ADJUSTMENT WALL ADJUSTMENT RETURN PANEL TRAY SIZE WALL ADJUSTMENT TRAY EDGE TO WALL CHANNEL 1 750mm 0 2 915mm 17 15mm 2 820mm 5 10 820mm 4 13mm 3 915mm 6 13 750mm 4 13mm 4 915mm 0 11 915mm 11 21mm 5 1000m...

Page 4: ...top K4000 Pivot Block K2004 Handle Replacement Screw Pack 2 3 Sided Chrome White K2271 4x35mm Screws Screw Caps 4x10mm screws Wall Plug Concrete Return Panel 1200 Door All doors except 1200 Lower door seals K6808 20 PCS 8 PCS 8 PCS 12 PCS PIVOT 2 SIDED SHOWER COMPONENT LIST ...

Page 5: ...el prior to fastening Mark wall profile Acrylic Shower Layout Ensure you read BEFORE YOU START section on page 3 Refer to Page 3 Table A B will give measurements for your specific installation B Fasten wall profiles for return and door panels A ...

Page 6: ...ed corner post position for your specific shower install Fasten this join parallel at corner Corner post must be plumb for alignment of magnetic seal B Finally adjust shower door in wall profiles and square up door to frame Drill and fasten door frame and return panel to wall profiles 3 B Ø3 2mm A ...

Page 7: ...7 4 5 Apply silicone to join as indicated Seal the join between wall profile and frame 150mm up from base on both sides ...

Page 8: ... Wall Plug Concrete Replacement Screw Pack Chrome White K2271 Wall Channel K7102 Back Door Seal K7072 Back Door Seal Stop K4000 Pivot Block K2004 Handle 1200 Door All doors except 1200 8 PCS 8 PCS 8 PCS 09 07 08 10 PIVOT 3 SIDED ALCOVE SHOWER COMPONENT LIST 3 SIDED ALCOVE ...

Page 9: ...door channel and fasten end caps 04 to top and bottom Back of Door Position of wall profiles to door frame 2 NOMINAL TRAY SIZE TRAY TYPE TRAY ACTUAL WIDTH 1mm LINER TO LINER MEASUREMENT SCREEN MIN MAX EXTENSION AT WALL 2 SIDES OF FRAME 810 L P 812mm 786mm 769mm 784mm 8 5mm 900 L P 902mm 876mm 860mm 890mm 8mm 1000 L P 1002mm 976mm 960mm 990mm 8mm 1200 L P 1202mm 1176mm 1155mm 1185mm 10 5mm 04 ...

Page 10: ...10 3 Layout Mark wall profile holes both sides Predrill liner with 2mm bit B A Fasten wall profiles Apply silicone bead down back of channel prior to fastening 08 09 ...

Page 11: ...ten door frame to wall profiles Door seal full width of door Notch out glass flange by 12mm each end of door Trim each side of pivot 1 Plumb and square up door to frame 2 Adjust evenly to both wall profiles 08 09 ...

Page 12: ...one to outer join as indicated Seal the join between wall profile and frame 150mm up from base on both sides CONTACT Freephone 0508 639 5463 Phone 09 444 2053 Fax 09 443 0044 Email info newline co nz www newline co nz ...

Reviews: