8) Troubleshooting

Symptom

Possible Cause

Corrective Action

Section

A. Battery requires excessive  

     re-charge time

1.Load at or near max. 

   recommended load providing 

   minimal current available for 

   charging

1.Reduce load or split load between 

   two separate DIN UPS units

2.Charging level current set to low

2.Adjust “Battery Charging Level” 

   control knob to higher level

B. Load turns off after a couple  

    of seconds when running  

    on battery

1.Time buffer set to incorrect position

1.Verify correct setting with manual

2.Batteries not charged, due to high 

   load demand

2.Reduce load or split load between 

   two separate DIN UPS units

C. No absoprtion voltage

1. Absorption jumper not installed

1. Install provided jumper in  

    position 6

D. Unit does not turn on

1. AC input is 115 VAC, no  

    jumper wire installed 

1. Install 115V jumper wire across j1 

    and j2

E. Trips AC input breaker

1. AC shorted to case

1. Verify correct AC input wiring

2. Defective unit

2. Contact technical service

F. No output

1. DC output wired backwards  

    or shorted

1. Remove AC input and check DC   

    wiring

2. No AC input

2. Verify correct AC input and 

    jumper wire installed if powering   

    from 115 VAC

3. Excessive temperature or  

    blocked ventilation

3. Improve ventilation, unblock 

    vent holes

4. Defective unit

4. Contact technical service

G. No voltage on battery  

     output terminals

1. No battery installed (voltage 

    required for battery output to  

    turn on)

1. Install batteries

2. Missing or blown battery  

    wiring fuse

2. Replace missing or blown battery    

    wiring fuse

H. Diagnosis LEDs always blinking 1. Normal operation

1. Refer to Chart 2: Diagnosis Table

9) Warranty

Newmar warrants that the DIN-UPS 24-20 DIN Rail UPS to be free from defects in material and workmanship for two years 

from date of purchase. If a problem with your DIN-UPS 24-20, or if you have any questions about the installation and 

proper operation of the unit, please contact NEWMAR’s Technical Services Department:

Phone: 714-751-0488 - From the hours of 7:30 a.m. to 5:00 p.m. weekdays, P.S.T.; 

Fax: 714-957-1621

E-mail: techservice@newmarpower.com

Summary of Contents for DIN-UPS 24-20

Page 1: ...fety Information 4 3 Installation Wiring 4 A Mounting 4 B Wiring 5 1 AC Input 5 2 Output 5 C Form C Contact 5 D Temperature Compensation Sensor 6 4 Settings 6 A Battery Type Charge Curve 6 B Time Charge Current Limit Battery Charge Level 7 C Time Buffering Battery Run Time 8 D System Setttings 8 5 Operation 8 A Battery Start w o AC Present Push Button 8 B Status Indicator LED s 8 C LVD 9 6 Protect...

Page 2: ...le to the load remaining power is available for battery charging See page 6 for details D Battery Temperature Sensor optional Plug in port RJ 45 See page 6 for details E Communication Modbus contact factory for more information F Output to Load two terminals each for plus and minus utilize dual wiring when load is more than 15 feet from unit Note the unit has a load priority circuit all produced p...

Page 3: ... Charge Enaable Jumper Insert Position Open Lead Default None 26 76 VDC Pos 6 28 8 VDC Sealed Lead Insert Jumper Pos 1 Pos 1 27 0 VDC Pos 6 28 8 VDC Gel Battery Insert Jumper Pos 2 Pos 2 27 6 VDC Pos 6 28 8 VDC Ni Cad Insert Jumper Pos 3 Pos 3 See note below Pos 6 31 0 VDC 1 55 VPC x 20 Cells 1 2 3 4 7 5 6 1 2 3 4 7 5 6 1 2 3 4 7 5 6 1 2 3 4 7 5 6 1 2 3 4 7 5 6 1 2 3 4 7 5 6 1 2 3 4 7 5 6 1 2 3 4 ...

Page 4: ... input See specification section for maximum AC input draw for your input voltage for circuit breaker sizing CAUTION Hot surface Avoid touching the DIN UPS case while operating at or near its full load capacity Remove AC and battery power and allow DIN UPS at least 10 minutes to cool before removing from DIN Rail 3 Installation Wiring A Mounting The unit is designed for 35 mm DIN rail mounting in ...

Page 5: ...25 amp fuse be installed on the hot leg at battery If using both sets of battery terminals on DIN UPS i e two pairs of wires recommended for long wire runs connect both hot wires to one side of battery fuse Battery Output wires size recommended 14 AWG Terminal Block maximum wire size recommended 10 AWG C Alarm Contacts Form C Isolated Form C Contacts for remote monitor Activate upon a AC power fai...

Page 6: ...rial port remove the access tab in the front panel decal labeled COM MODBUS see Figure 8 Contact 1 AC Fail LED 2 Fault Battery LED 3 Diagnosis LED Input 5 6 5 7 8 9 8 10 AC only closed open open closed off on 2 Blink Pause AC Batt closed open closed open off off 1 Blink sec Batt only open closed closed open on off off Low Batt open closed open closed on on off Labeled Low Battery or Battery Replac...

Page 7: ... produced power is made available to the load remaining power is available for battery charging To set use small slotted screw driver to rotate selector dial Set dial between 10 to 20 of battery capacity Amp Hours Figure 10 Current Limit Battery Charge Level Dial Table 4 Battery Selection Absorption Charge Figure 9 Battery Type Insert jumper tabs for battery selection L N INPUT i A FA LO OR RE DIA...

Page 8: ...k up i AC OK AC Fail LED Off or ii Operating on battery backup power AC Fail LED On red 2 Low battery or battery replacement LED illuminates when Low Battery capacity less than 30 Bad connection to battery Battery requires replacement 3 diagnosis LED Charger output status system diagnosis and Fault mode diagnosis by blink code Table 6 on next page Figure 12 Battery Start LED Function Setting Batte...

Page 9: ...nit limits the output current Low voltage disconnect protects battery from deep discharge Monitoring Control State LED Diagnosis No 3 LED Battery Fault No 2 Charging Type Float 1 Blink sec OFF Absorption 2 Blink sec OFF Bulk 5 Blink sec OFF System Auto Diagnosis Reverse polarity or high battery Voltage 1 Blink pause ON Battery Not connected no output power 2 Blink pause ON Battery shorted cell 3 B...

Page 10: ...solated from case Front Panel LED Indicators Power Source operating on back up red AC Fail LED Battery and System Diagnostics via blink code Settings Selectors Battery Type AGM Sealed Lead Open Lead Acid Flooded Gel Cell and Ni Cad 20 Cell Battery Charge Current Limit 20 100 of charge amperage rating Back Up Run Time on Batteries Programmed time limit 1 60 min Or Until LVD disconnect 18V Power Res...

Page 11: ... and j2 E Trips AC input breaker 1 AC shorted to case 1 Verify correct AC input wiring 2 Defective unit 2 Contact technical service F No output 1 DC output wired backwards or shorted 1 Remove AC input and check DC wiring 2 No AC input 2 Verify correct AC input and jumper wire installed if powering from 115 VAC 3 Excessive temperature or blocked ventilation 3 Improve ventilation unblock vent holes ...

Reviews: