4.2  INSTALLATION

Please read completely before beginning.

4.1.   Unpack  and  inspect  the  Newmar  Fuse
Panel  for  possible  damage  incurred  during
shipping.   If  damage  is  found,  file  a  claim
immediately  with  the  carrier  and  notify
Newmar.

4.2.   Once  the  panel  is  unpacked,  verify that
there are two mounting  brackets.    Fasten  the
mounting  brackets  to  the  sides  of  the  fuse
panel  using  the  screws  provided,  such  that  it
will fit the rack you wish  to mount  the panel  in.
Single  rack  height  panels  have  a  universal
bracket  that  allows  the  panel  to  be  mounted
on either 19" or 23" wide equipment  racks  and
can be installed for  flush  mounting  of the fuse
panel, or for a 5" offset mounting.

4.3.   Mount the  fuse  panel  on  the  equipment
rack  using  the  thread  forming  #12-24  rack
mounting screws and lock washers provided.

WARNING:

  For  safety  reasons  all  wiring

should  be  done  with  the  power  source
removed  (when  possible.)

4.4.   Remove the distribution fuse feeding the
input  cables  that  are  to  be  connected  to  the
new  panel.   Using  input  cables  specified  by
the Job Engineer, hook up the input cables to
the  input  terminal  block  on  the  fuse  panel.
This panel has two sets of inputs.   Torque  _”
steel nuts to 5.5 ft-lbs.

Please  be  sure  to  observe  the  proper
polarity.

4.5.   The  battery  outputs  are  available  at  the
terminals blocks at the rear of the panel.   Each
fuse  position  is  numbered  and  that  fused
circuit  is  available  at  the  terminal  block
position with the same number.

4.6. All battery return (ground)  connections  are
terminated  on  the  isolated  battery  return  on
the
rear of the panel.   Note that these returns  are
isolated from the chassis.  

4.7.   For  this  fuse  panel  you  have  common
(C), normally closed (NC), normally  open  (NO)
alarm  extensions  (two  sets  of  dry  “C”
contacts.) You  have  ground  activated external
alarm  and  battery  activated  external  alarm
(alarms that originated outside the panel.)

4.8.  

CHASSIS GROUND;

   For  safety  reasons,

and  as  recommended  by NEBS,  the  chassis
should  be  electrically  connected  to  the  rack
ground.   From  step  4.3.  the  panel  should
already  be  ground  to  the  rack  via  the  #12-24
thread  forming  rack  screws  and  outside  tooth
lock washers.  In  addition  to grounding  via the
mounting  brackets,  it  is  recommended  you
ground the chassis  using  a ground  cable  and
the #10 bolt and locks on side of  chassis  (#10
screw torque; 2ft/lbs or 2.7Nm.)

4.9.   Power  up  the  panel  by  installing  the
distribution  fuse  supplying  the  panel.    The
panel should power up and have  no red LEDs
illuminated.   Green power LEDs should be lit.

4.10.  Install panel output distribution  fuses  as
required.   Use  the  provided  designation  card
to  keep  a  record  of  which  equipment  is
connected  to  which  circuit  and  what  the  fuse
rating is.

4.11.   If  you  wish  to  verify  the  Fuse  alarm
circuit,  you  can  insert  a  blown  or  open  fuse
into one of the empty fuse holders.  A red Fuse
Alarm  LED  should  light  on  the  faceplate  and
the alarm extension relay should  activate and
extend appropriate alarm. If  you wish  to  verify
the EXT Alarms you can connect  GND or -BAT
and  the  red  EXT  Alarm  should  light  on  the
faceplate  and  the  alarm  extension  relay
should activate and extend appropriate alarm.

Note:

 If you have any questions,  suggestions,

or  problems,  please  don't  hesitate  to  call
Newmar Technical  Support  at (714)  751-0488
or  contact  us  through  the  Internet  at
http//www.newmartelecom.com.  Your  input
helps us  in our ongoing  product  improvement
process that benefits both of us. 

Thank You

.