Add 3x 1280 x 2” x 1.5” with decking screws onto the inside of 90*90 horizontal posts to
hold the base.
Keep the top of your 2”x 1.5” down 35mm from the top of your 90*90 horizontal posts
Lift the base on top of this new structure and fix the decking screws onto the sides, with 2
screws in each panel on the edges
The overhanging 3” x 1.5” from the bottom of the base will be to the tower side of the
tractor, and will be screwed up into the horizontal post of the main tower.
Step 9: Finishing the structure and adding the base
3 panels underneath, these are lower in size and will fit the same your previous step (7)
‘Fix this to the upright post using 60mm decking screws, use 2 boards in each panel.
Repeat this step on the front; this panel will have an opening underneath. If you ensure that
this is 1.2 this will mean your sides should fit in perfectly.’
Step 10: Adding the Modules:
Attaching commercial slide: