To assemble GV-HR110 follow the instructions below:
1) Remember to switch off the electricity before
opening the aggregate.
2) An airtight waterseal must be mounted in a frost-free
place to compensate for the pressure from the
ventilation unit.
3) The height of the waterseal must be at least 50 mm.
4) The pipe drain must fall freely to the sewer drain.
5) Pour 1 litre water into the condensation container of
the machine to check that the water flows without
stoppage. The waterseal must be checked for water
every year before the cold season begins.
6) If the waterseal is mounted where the temperature can
fall below 0 C°, then the waterseal must be protected
against frost with a thermostat and an electric heating
element that switches on when the temperature falls
below +2 °C.
.
IMPORTANT
.
IMPORTANT
.
IMPORTANT
.
IMPORTANT
.
7) Set the amount of incoming 1 - and outgoing air
before using the facility. It is very important that the
air balance in the house is correct.
8) It is recommended to close the air valves etc. until
the machine has been started up and the settings
made.
9) The supplied electric preheater has to be installed
in fresh air duct and connected to the AHU. It is
important to set the settings regarding the heater in the
control panel. See “ User manual, 4.5 User Menu,
2-Reheater “.
Follow the instruction in this manual. If the drain is not
set up in accordance with the manual, NIBE will not
be liable for any consequential damages pertaining to
the NIBE facility.
.
IMPORTANT
.
IMPORTANT
.
IMPORTANT
.
IMPORTANT
.
Subject to Technical Modifications of GV-HR110