19 - 120VAC POWER WIRING

Table 1 - MAXIMUM RUN (FT) PER WIRE GAUGE 

110V AWG 
MAX RUN (ft) 

 14 

 12 

 10 

 8 

 6 

 4 

 180 

 280 

 460 

 700 

 1150 

 1800 

Deleting all Nice transmitters from the Nice Plug-In Receiver Memory. 

All programmed remote controls may be removed from the Nice plug 

in receiver memory . This procedures need to be performed at the gate 

controller. 

1.

 Press and hold the button on the side of the Nice receiver until the led on 

the Nice receiver illuminates green and keep the button pressed. 

2.

 Watch the led and on the receiver and verify the following sequence in the 

led. 

3.

 Within 4 seconds after pressing the button (approx.) the green led 

illuminates. 

4.

 Within 8 seconds after pressing the button (approx.) the green led turns 

off. 

5.

 Within 12 seconds after pressing the button (approx.) the green led starts 

flashing 

6.

 Count the green led flashes on the Nice receiver. On EXACTLY the 3

rd 

flash, 

release the button on the Nice receiver. 

7.

 It is recommended to test the Nice remote controls, if available, with Nice 

plug in receiver to verify that it no longer affects the gate controller.

DO NOT WIRE AC POWER TO THE 1050 CONTROL BOARD! 

THE CONTROL BOARD OPERATES ON 10 - 35 VDC ONLY! 

This section intended for residential systems where a 120VAC 

transformer will be used

To reduce the risk of SEVERE INJURY or DEATH: 

•  Disconnect power to the gate operator by manually opening its dedicated 

circuit breaker before making any mechanical or electrical adjustments. 

•  Use a 20 Amp dedicated circuit breaker for each installed gate operator. 

•  Open dedicated circuit breaker supplying power to this gate operator 

BEFORE a new installation or making any modifications to an existing 

installation of this gate operator. 

•  All wiring connections MUST be made by a qualified individual 

•  Run individual circuits in separate U.L. listed conduits. Do not combine 

high voltage (120VAC) power wiring and low voltage (+12VDC to +24VDC) 

control wiring in the same conduits. 

•  Use the information in table 1 to determine high voltage wire size 

requirements. The distance shown in the chart is measured in feet from the 

operator to the power source. If power wiring is greater than the maximum 

distance shown, it is recommended that a service feeder be installed. 

When large gauge wire is used, a separate junction box must be installed 

for the operator connection. The wire table is based on stranded copper 

wire. Wire run calculations are based on a 110 VAC power source with a 

3% voltage drop on the power line, plus an additional 10% reduction in 

distance to allow for other losses in the system.

The gate operator system should be grounded through the earth ground 

in the AC mains wiring system (GREEN WIRE). This ground connection will 

prevent dangerous currents from appearing on the metal control box, the 

motor, or the gate itself. 

DO NOT WIRE AC MAINS POWER TO THE METAL CONTROL BOX 

WITHOUT AN EARTH GROUND CONNECTION! 

20 - SOLAR PANEL CHART

Daily cycles 

1-10

1-20

1-40

1-60

1-80

80+

5 watt solar panel

*

10 watt solar panel

*

20 watt solar panel 

(requires regulator)

*

30 watt solar panel 

(requires regulator)

*

40 watt solar panel 

(requires regulator)

*

1.5 amp battery 

charger

*

10 amp battery 

charger

*

Note: Double the amount of solar wattage for dual gate operators

This Apollo Gate Operator is 12 Volt DC (Direct Current) powered. A 12 Volt 
sealed battery (33 ampere hour minimum for AC charged systems, 70 ampere 
hour minimum for solar charged systems) with connecting posts located on the 
top is recommended. 
The following table should be used as a guide for capacity of operation of 
operators only, additional options and accessories may reduce the daily usage. 
Please note that the charge capability of solar panels will vary with different 
geographical locations.

Nice Apollo operators with the 1050 board that are used in solar applications 
need to be put into “Standby” mode.

To do this, press Functions – scroll to #8 “Standby” – Press OK – Scroll to 
desired amount of time before system enters Standby mode – Press OK. Once 
this is done, the operator will enter a Standby mode after the set time when the 
operator is not moving or in the auto-close countdown.

Things to note in Standby:

1. Display will be off and only a “heartbeat” will be present at the LED OK
2. Voltage at #20 (24 volts) and #38 (12 volts) will turn off - 

DO NOT POWER 

ENTRY OR EXIT DEVICES HERE 

3. BlueBus connection is non functional         
4. Master/Slave syncing is non functional (used for commercial operators 

only)

Connection of the solar panel(s) may be made at the top left corner of the 
board at “Solar P” (regulated charging to the “Battery” via the controller in the 
board) – note that the maximum output of the regulator in the 1050 board is 
1.5A.  If the installation requires larger than a 30W solar panel – an off-board 
regulator should be used and connected directly to the battery.

Summary of Contents for H12-ETL-1K

Page 1: ...Nice Apollo Swing Gate Opener Vehicular Swing Gate Operator Revision 1 0 0 0_2 2014 Model H12ETL 1K...

Page 2: ......

Page 3: ...ION 10 11 CONTROL BOX MOUNTING 11 12 MOTOR WIRING 11 13 LIMIT AND MOTOR CONNECTION TO THE BOARD 11 14 INCOMING POWER WIRING 12 15 LIMIT SWITCH ADJUSTMENT 13 16 REPLACE COVER 13 17 LEARNING MODE 14 18...

Page 4: ...ction Dry contact inputs are provided for loop probe and photoelectric detectors as well as edge sensors guard station and fire department control of gate opening and closing Voltage outputs 12VDC and...

Page 5: ...he moving gate system No entry into the gate is ever authorized and should be prevented by whatever measures are required for that specific installation Care should always be used during installation...

Page 6: ...nal gate types 4 3 15 Any existing manual gate latches shall be removed or disabled when an automatic gate system is installed Use only mag locks controlled by the system 3 3 Gate system safety device...

Page 7: ...nt any device that operates the gate opener where the user can reach around over or through the gate to operate the controls Controls should be mounted at minimum 8 feet away from any moving part of t...

Page 8: ...IDENTIFICATION Accessory Output Connections Power Input Connections Motor Output Connections BlueBus Connection Master Slave Connection Accessory Input Connections Control Box 11111B Earth Ground H12...

Page 9: ...size or hinge location Remove the cover from the motor assembly and store in a safe place with screws Remove motor assembly from the mounting bracket B A 17 3 4 B A inches 3 9 16 4 5 16 6 7 7 8 9 13 1...

Page 10: ...ly Disengage the manual release as shown With the gate in the closed position push the arm towards the gate as shown Tack weld or C clamp the gate bracket in place Permanent welds or bolts should be c...

Page 11: ...k green limit common yellow motor encoder signal blue common orange open limit switch white close limit switch 12 MOTOR WIRING Mount the control box within 4 feet of the motor assembly Do not mount th...

Page 12: ...onnect wires to the battery terminal block The positive wire of the battery connects to the left terminal marked Note If the battery is connected backwards a red LED will illuminate below the terminal...

Page 13: ...of the Control board hold the button down until the gate reaches the fully intended open position Adjust the Open Limit Switch until the GREEN light illuminates on the front of the control board The F...

Page 14: ...irection MUST be set prior to learning the board 2 Press and hold the Open or Close button on the gate controller until the gate is 50 open 3 Press ENTER to allow the control board to scan for attache...

Page 15: ...ars hard shutdown GUARD STATION Guard Station Open 34 Dry contact input for a guard station open switch Momentarily shorting the digital input to GND opens the gate to the full open position with the...

Page 16: ...cting other assigned remote controls This procedure needs to be performed at the Nice Plug In Receiver with the affected Nice remote control 1 Press and hold the button on the side of the Nice receive...

Page 17: ...d for the operator connection The wire table is based on stranded copper wire Wire run calculations are based on a 110 VAC power source with a 3 voltage drop on the power line plus an additional 10 re...

Page 18: ...g edge of the closing gate The EXIT sensor input is provided to activate to open the gate or re open a closing gate upon sensing an exiting vehicle Figure FIRE DEPT INPUT 21 2 Magnetic lock connection...

Page 19: ...ty equipment and connections Clean equipment and connections 22 6 Improper broken inadequately supported equipment wiring and conduit loose connections of terminals and loose ferrules 22 7 Poor mechan...

Page 20: ...Photocells Figure LAYOUT FOR IN GROUND LOOPS Entrapment Protection Inputs Typical Installation Diagram Utilizing Photocells Figure LAYOUT FOR PHOTOCELLS Loop Safety Loop Safety Loop Shadow Loop Exit...

Page 21: ...at the control panel before making any electric service power connection Be aware of all moving parts and avoid close proximity to any pinch points Know how to operate the manual release Adjust the un...

Page 22: ...Stop gate movement Close the gate Figure GENERAL BOARD OVERVIEW THE PROGRAMMING BUTTONS INDICATED IN THE ABOVE REFERENCE SHOULD BE USED ONLY AFTER UNDERSTANDING THE MANUAL AND ITS RELATION TO THE PROG...

Page 23: ...itivity of sudden impact force to the moving gate on a scale of 1 to 10 1 being most sensitive ESC Exit the FORCE menu 26 2 Speed Max Sets the limit of maximum allowed gate speed on a scale of 20 to 1...

Page 24: ...dvance Settings The following settings are available for customizing the gate operator as required by the customer s installation requirements Set Language English Spanish French Set clock 12H 24H Set...

Page 25: ...perator or system intended for use in a commercial location or building such as a multi family housing unit five or more single family units hotels garages retail store or other building servicing the...

Page 26: ...Table 3 SYMPTOM S POSSIBLE SOLUTION Check that power to the circuit board is turned ON Check terminal block wiring for loose or broken wires If voltage measures OK check the terminal block Check the...

Page 27: ...27 1 1 2 2 A A B B COMPANY NICE APOLLO NAME CONTROL BOX GENERAL OVERVIEW 18 22 18 18 8 32...

Page 28: ...LE POLE 1115 1 4 SWITCH PUSH BUTTON CNTRL BOX 1119 1 5 1050 CIRCUIT BOARD 1050 1 6 1050 BOARD MOUNT KIT 10055090 1 7 NICE RECEIVER 318NPI 1 8 1 1 2 2 A A B B TITLE Company 2 6 8 3 7 4 5 1 Note Control...

Page 29: ...the information from the dated proof of purchase receipt to confirm the warranty period or the technician will confirm your extended warranty period through your registration information on file The t...

Page 30: ...30...

Page 31: ...e and has tested the gate to make sure that the gate stops and reverses a short distance with minimal resistance applied Approximately 40 lbs on a swing gate at the end of the gate 8 The installer has...

Page 32: ...Contact us Nice Group USA Inc 12625 Wetmore Road Suite 218 San Antonio TX 78247 Ph 1 210 545 2900 Fax 1 210 545 2915 www niceapollo com www facebook com NiceApollo...

Reviews: