Shredders
8. - Instructions for work
53
TBE GBseries 102
JN070AGB B
- Before the machine enters vegetation:
• Engage the tractor PTO and slowly increase the
speed up to 540 min
-1
.
• Wait until this rotation speed is reached.
- Lower the tractor three-point linkage.
Using the offset
- Slightly lift the machine off the ground using the
tractor lift linkage.
- Offset machine.
- Lower the tractor three-point linkage to rest the
machine on the ground.
8.3.1 Drive speed
Groundspeed must be adapted to the encountered
working conditions.
If the machine starts vibrating oddly during
work, immediately stop and check the
condition of the rotor, the cutting tools and
the balancing ballast. Excessive vibration
can cause physical harm to the user.
Side offset manoeuvres must only be carried
out with the machine in raised position and
working height control elements off the
ground.
Check cutting tools before each use and
immediately after hitting an obstacle.