17
4.6
T
ARGET
I
NSTALLATION AND
A
LIGNMENT
NOTE: It is very important that the
rods be installed on the right hand
side of the sprayer.
The sprayer must be level when
installing the UC4+ Roll Control
System. The sprayer booms
should be level as well, parallel to
the sprayer’s lift frame.
1.
To ease the installation of the UC4+
Roll Control system, unfold the sprayer
on a level area and lower the center
section to three or four feet above the
ground. A ladder or step will also be
required to complete the installation.
Figure 17 – Roll Control Items
Figure 18 – Typical Roll Control Install
Bumper
Frame
Target
Roll
Control
Frame
Sprayer Parallel Lift
Frame
Sensor
Bracket
Roll
Sensor
Spring
Target
Boom Centre
Frame
Frame Target (B07)
Spring Target (B12)
Sensor Bracket (B11)
Remove the Rubber
Bumper
Summary of Contents for UC4+
Page 12: ...9 Figure 3 Hydraulic Plumbing Schematic ...
Page 30: ...27 Figure 36 Load Sense Plumbing on some JD4710 Rear of Sprayer Front view of block H06 F03 ...
Page 32: ...29 Figure 38 2003 Load Sense Line Connection H06 F03 ...
Page 41: ...38 5 3 ITEM C3 44656D CABLE VALVE VARIABLE RATE DT ...
Page 42: ...39 5 4 ITEM C4 44651 VALVE EXTENSION CABLE 5 5 ITEM C10 44650 14 POWER CABLE ...
Page 43: ...40 5 6 ITEM C12 44658 01 UC4 JD JUNCTION CABLE ...
Page 44: ...41 5 7 ITEM C70 44658 08D UC4 ROLL BIAS VALVE CABLE DT ...
Page 45: ...42 5 8 ITEM C71 44647 CABLE UC3 SENSOR ROLL BIAS ...
Page 47: ...44 Figure 51 Cable C12 44658 01 BEFORE Modification ...
Page 48: ...45 Figure 52 Cable C12 44658 01 AFTER Modification ...