23
10.
Mount the NORAC valve (
V01
) on the
sprayer using the valve mounting bracket
(
B10
).
11.
Thread a nut onto the short threads of each
of the threaded studs.
12.
As shown in
Figure 30,
screw the short
side of the threaded rods into the bottom of
the valve block and tighten the hex nuts tight
to the valve block.
13.
Place the valve block onto a frame member,
with the studs extending to the other side of
the member.
14.
Slide the flat bar from the bracket over the
studs and install a spring washer and nut
onto each of the studs to hold the bracket in
place.
15.
Tighten the two nuts so the valve block is
held on tight and cannot move.
16.
Cut excess off of the rods, if necessary.
If you wish to use bolts, the bolts
should thread into the valve block
at least 3/8". The valve mounting
holes are drilled and tapped 3/8
NC-1" deep. The rule of thumb for
bolt length is 1-1/2" longer than the
tube size.
The recommended location for the
valve is on the angled cross tube of
the parallel linkage on the sprayer.
Orient the valve block so the "A"
and "B" ports face towards the
boom (Figure 31).
You must ensure no hydraulic
components will interfere with any
sprayer parts or be pulled tight at
any time.
Figure 30 – Valve Mounting Location
Figure 31 – Valve Mounting Example
Summary of Contents for UC4+
Page 12: ...9 Figure 3 Hydraulic Plumbing Schematic ...
Page 30: ...27 Figure 36 Load Sense Plumbing on some JD4710 Rear of Sprayer Front view of block H06 F03 ...
Page 32: ...29 Figure 38 2003 Load Sense Line Connection H06 F03 ...
Page 41: ...38 5 3 ITEM C3 44656D CABLE VALVE VARIABLE RATE DT ...
Page 42: ...39 5 4 ITEM C4 44651 VALVE EXTENSION CABLE 5 5 ITEM C10 44650 14 POWER CABLE ...
Page 43: ...40 5 6 ITEM C12 44658 01 UC4 JD JUNCTION CABLE ...
Page 44: ...41 5 7 ITEM C70 44658 08D UC4 ROLL BIAS VALVE CABLE DT ...
Page 45: ...42 5 8 ITEM C71 44647 CABLE UC3 SENSOR ROLL BIAS ...
Page 47: ...44 Figure 51 Cable C12 44658 01 BEFORE Modification ...
Page 48: ...45 Figure 52 Cable C12 44658 01 AFTER Modification ...